10.4. Thermal insulation of refrigerant piping

Be sure to add insulation work to refrigerant piping by covering liquid pipe and gas
pipe separately with enough thickness heat-resistant polyethylene, so that no gap
is observed in the joint between indoor unit and insulating material, and insulating
materials themselves. When insulation work is insufficient, there is a possibility of
condensation drip, etc. Pay special attention to insulation work in the ceiling ple-
num.
[Fig. 10.4.1]
C
B
A
D
E
A Steel wire
C Oily mastic asphalt or asphalt
E Outer covering B
Glass fiber + Steel wire
Heat
insulation
Adhesive + Heat - resistant polyethylene foam + Adhesive tape
material A
Indoor
Vinyl tape
Outer
Floor exposed Water-proof hemp cloth + Bronze asphalt
covering B
Outdoor
Water-proof hemp cloth + Zinc plate + Oily paint
Note:
When using polyethylene cover as covering material, asphalt roofing shall
not be required.
No heat insulation must be provided for electric wires.
[Fig. 10.4.2]
B
A
C
D
E
A Liquid pipe
B Gas pipe
D Finishing tape
E Insulator
[Fig. 10.4.3]
11. Wiring (For details, refer to the installation manual of each indoor/outdoor unit and controller.)

11.1. Caution

1 Follow ordinance of your governmental organization for technical standard re-
lated to electrical equipment, wiring regulations and guidance of each electric
power company.
2 Wiring for control (hereinafter referred to as transmission line) shall be (5 cm or
more [2 in or more]) apart from power source wiring so that it is not influenced
by electric noise from power source wiring. (Do not insert transmission line
and power source wire in the same conduit.)
3 Be sure to provide designated grounding work to the outdoor unit.
4 Give some allowance to wiring for the electrical part box on the indoor and
outdoor units, because these boxes are sometimes removed at the time of
service work.
5 Never connect the main power source to terminal block of transmission line. If
connected, electrical parts will burn out.
6 Use 2-core shield cable for the transmission line. If transmission lines of differ-
ent systems are wired with the same multiplecore cable, the resultant poor
transmitting and receiving will cause erroneous operations.
7 Only the transmission line specified should be connected to the terminal block
for outdoor unit transmission.
Erroneous connection does not allow the system to operate.
14
B Piping
D Heat insulation material A
E
E
A
B
D
C Electric wire
Penetrations
[Fig. 10.4.4]
<A> Inner wall (concealed)
A B
<C> Outer wall (exposed)
E
B
I
<E> Roof pipe shaft
G
D
B
H
F
A Sleeve
C Lagging
E Band
G Sleeve with edge
I Mortar or other incombustible caulking
J Incombustible heat insulation material
When filling a gap with mortar, cover the penetration part with steel plate so that
the insulation material will not be caved in. For this part, use incombustible materi-
als for both insulation and covering. (Vinyl covering should not be used.)
Insulation materials for the pipes to be added on site must meet the following
specifications:
ø6.35 to 25.4 mm [1/4 to 1 in]
10 mm min. [13/32 in min.]
Thickness
Temperature Resistance
*
Installation of pipes in a high-temperature high-humidity environment, such as
the top floor of a building, may require the use of insulation materials thicker
than the ones specified in the chart above.
*
When certain specifications presented by the client must be met, ensure that
they also meet the specifications on the chart above.
8 When connecting a System Controller to outdoor units or performing a group
operation of indoor units that are connected to different outdoor units, a trans-
mission line for centralized control is required. When using a transmission line
for centralized control, connect the transmission line (non-polar 2 core wire) to
all TB7 terminals between all outdoor units.
9 Grouping is set by operating the remote controller.

11.2. Control box and connecting position of wiring

1 Outdoor unit
1. Remove the front panel of the control box by removing the 4 screws and push-
ing it up a little before pulling it out.
2. Connect the indoor - outdoor transmission line to the terminal block (TB3) for
the indoor - outdoor transmission line.
If multiple outdoor units are connected in the same refrigerant system, daisy-
chain TB3 (M1, M2, ground terminal
indoor - outdoor transmission line for the outdoor units to TB3 (M1, M2, ground
terminal
) of only one of the outdoor units.
3. Connect the transmission lines for centralized control (between the centralized
control system and the outdoor unit of different refrigerant systems) to the
terminal block for centralized control (TB7). If the multiple outdoor units are
connected to the same refrigerant system, daisy-chain TB7 (M1, M2, S Termi-
nal) on the outdoor units in the same refrigerant system. (*1)
(Unit: mm [in])
<B> Outer wall
D
C
A B
<D> Floor (waterproofing)
D
F
G
B
<F> Penetrating portion on fire limit and
boundary wall
I
J
A
1000
1000
[39-3/8]
[39-3/8]
B Heat insulating material
D Caulking material
F Waterproofing layer
H Lagging material
Pipe size
ø28.58 to 41.28 mm [1-1/8 to 1-21/32 in]
15 mm min. [19/32 in min.]
100°C min. [212°F min.]
) on the outdoor units. Connect the

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

City multi puhy-p-tjmu-aCity multi puhy-p-tjmu-a-bsCity multi puhy-p-yjmu-aCity multi puhy-p-yjmu-a-bsCity multi puhy-p72tjmu-aCity multi puhy-p72tjmu-a-bs ... Show all

Table of Contents