MANDÍK 0789-0010 Installation, Commissioning Maintenance

Cpv compact air handling units
Table of Contents

Advertisement

Quick Links

MANDÍK CPV Installation, commissioning, and maintenance
INSTALLATION
COMMISSIONING
MAINTENANCE
IZU 02/2021
CPV Compact Air Handling Units
MANDÍK, a.s., www.mandik.cz
R
R
1

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the 0789-0010 and is the answer not in the manual?

Questions and answers

Summary of Contents for MANDÍK 0789-0010

  • Page 1 MANDÍK CPV Installation, commissioning, and maintenance CPV Compact Air Handling Units INSTALLATION COMMISSIONING MAINTENANCE IZU 02/2021 MANDÍK, a.s., www.mandik.cz...
  • Page 2 MANDÍK CPV Installation, commissioning, and maintenance Contact: MANDÍK, a.s. Dobříšská 550 267 24 Hostomice Czech Republic tel: +420 311 706 706 fax: +420 311 584 810 email: mandik@mandik.cz service department email: service@mandik.cz © Copyright MANDÍK, a.s. 2021. Subject to change. IZU 02/2021 MANDÍK, a.s., www.mandik.cz...
  • Page 3: Table Of Contents

    MANDÍK CPV Installation, commissioning, and maintenance CONTENTS GENERAL ......................... 5 RELATED DOCUMENTS ....................6 GENERAL INFORMATION ....................6 UNIT IDENTIFICATION ....................6 DIMENSIONS OF THE UNIT .................... 8 CONNECTION DIMENSIONS ..................8 SAFETY ..........................8 HANDLING, TRANSPORT AND STORAGE ................ 9 ASSEMBLY AND INSTALLATION ..................
  • Page 4 MANDÍK CPV Installation, commissioning, and maintenance MAINTENANCE AND SERVICE INTERVALS ..............30 GENERAL OPERATION AND MAINTENANCE OF THE UNIT .......... 34 FANS ..........................35 FILTERS ........................35 DAMPERS, FLEXIBLE ELEMENTS .................. 37 HOT WATER COIL, COLD WATER COIL ................ 37 9.10 CONDENSER COIL, DIRECT EVAPORATOR COIL ............
  • Page 5: General

    MANDÍK CPV Installation, commissioning, and maintenance 1 GENERAL This manual uses graphics and symbols to highlight specific details. They include: This symbol indicates a potentially hazardous situation and an imminent health or safety hazard to personnel, the unit, or its components. This symbol indicates an electrocution hazard.
  • Page 6: Related Documents

    MANDÍK CPV Installation, commissioning, and maintenance 2 RELATED DOCUMENTS The following documents are attached to every delivered unit: • Warranty sheet • Installation, operation and maintenance manual • Technical specifications of the unit • Declaration of conformity • List of fasteners and other materials •...
  • Page 7 MANDÍK CPV Installation, commissioning, and maintenance Unit type designation: CPV12-30-11-7252-111-101 Outlets Damper equipment Filtration Cooling Reheating Unit size Unit type Unit size Reheating Cooling Filtration Damper equipment Air outlets 7252 1st character C = compact 1st-2nd character = * 100 = Vn [m3/h] XX = no heating XX = no cooling 1st character = type of supply filtration 1st character = mixing damper 1st character = SUP orientation...
  • Page 8: Dimensions Of The Unit

    MANDÍK CPV Installation, commissioning, and maintenance 3.2 DIMENSIONS OF THE UNIT The dimensions of the unit are calculated dynamically in the software per the specific order in steps of 1 mm. The specific dimensions of selected units are provided in the relevant technical specifications.
  • Page 9: Handling, Transport And Storage

    MANDÍK CPV Installation, commissioning, and maintenance • The air entering the unit contains aggressive gases or chemicals or the air temperature is below -30°C or higher than +50°C, or the return air humidity is excessively high (the unit is not designed for damp air service, such as in pool facilities, etc.) Access inside the equipment and conducting any work on the equipment are prohibited until the following are met: •...
  • Page 10 MANDÍK CPV Installation, commissioning, and maintenance the carrier’s delivery note. Failure to follow this procedure may result in denial of any claim involving damage during transport. • Units must be stored in dry, and clean covered premises, protected from rain and snow, and in which the ambient temperature does not drop below +5 °C;...
  • Page 11 MANDÍK CPV Installation, commissioning, and maintenance straps from slipping. Use tubing 40 to 45 mm in diameter. Use tubing with a minimum wall thickness of 5 mm. The minimum clamping angle of the strap to the upper edge of the unit is 50°. Only transport the unit in its horizontal working position.
  • Page 12: Assembly And Installation

    MANDÍK CPV Installation, commissioning, and maintenance 6 ASSEMBLY AND INSTALLATION 6.1 GENERAL • Only authorised personnel may assemble units. Personnel conducting assembly must comply with all valid technical regulations and legislation in the given country. For example: ČSN EN 45004, Act 174/68 Coll. •...
  • Page 13: General Stipulations Regarding Unit Placement

    MANDÍK CPV Installation, commissioning, and maintenance could result in a higher controlled working point for the fan and higher electric motor power usage. 6.2 GENERAL STIPULATIONS REGARDING UNIT PLACEMENT • The minimum space for basic maintenance and service is dependent upon the width of the doors as specified in the technical specifications for the given unit, or a minimum of 600 mm •...
  • Page 14: Connecting The Unit To Hvac Ductwork

    MANDÍK CPV Installation, commissioning, and maintenance 6.5 CONNECTING THE UNIT TO HVAC DUCTWORK The unit may only be connected to square ducts using flexible elements installed on every supply / return on the unit (to prevent the transmission of vibration), or to round ducts using round ports with gaskets that are installed on every supply / return on the unit.
  • Page 15: Hot / Cold Water Coil Connections

    MANDÍK CPV Installation, commissioning, and maintenance When a trap is installed outdoors, the piping system must be tempered, i.e. using an electrical heating cable. Proper configuration of trap height per the pressure values is as follows: Fig. 3 Vacuum trap with ball HL136NGG May be used at vacuum up to 2300 Pa.
  • Page 16 MANDÍK CPV Installation, commissioning, and maintenance blocks of the unit or the heat exchangers. Connections must be executed so that expansion of the piping as a result of temperature changes does not result in excessive loading of the ports. Two wrenches must be used to tighten connections. Thread deformation is a significant risk otherwise! A vent valve, if installed, must be located at the highest point on the hot / cold water supply line.
  • Page 17: Electrical Connections

    MANDÍK CPV Installation, commissioning, and maintenance Phosphate content converted to P , min. 15 mg.l 6.8 ELECTRICAL CONNECTIONS Any intervention into electrical panels or connection of the provided components may only be performed by personnel with professional qualifications under the valid legislation in the country of installation of the equipment! Individual components of the unit are typically wired from the factory to the terminals of the controller and tests (fans, sensors, actuators, thermostats, manostats, electric heater, etc.).
  • Page 18 MANDÍK CPV Installation, commissioning, and maintenance The mains connection schematic for models with a hot water coil is provided in Annex D. The mains connection schematic for models with an electric heater is provided in Annex E. The connection schematic for peripherals: the CO2 sensor, POL822 room unit, and exterior outdoor air temperature sensor, is provided in Annex F.
  • Page 19: Activities Prior To Commissioning

    MANDÍK CPV Installation, commissioning, and maintenance 7 ACTIVITIES PRIOR TO COMMISSIONING 7.1 GENERAL • The unit may only be commissioned by instructed and trained personnel and with full adherence to applicable safety regulations and standards. • Prior to commissioning, it is necessary to complete all the previous steps in the installation instructions.
  • Page 20: Inspecting The Unit Prior To Initial Start-Up

    MANDÍK CPV Installation, commissioning, and maintenance 7.2 INSPECTING THE UNIT PRIOR TO INITIAL START-UP LIST OF SERVICING OPERATIONS PRIOR COMMISSIONING AIR-CONDITIONING UNIT MANDÍK Order number: User: Date: Commissioning party: Project name: Serial number: Position: Address: Date of first start-up: OPERATIONS FOR THE UNIT IN GENERAL Completion of operation Opera Measured or set...
  • Page 21 MANDÍK CPV Installation, commissioning, and maintenance OPERATIONS FOR THE UNIT IN GENERAL – ELECTRICAL AND MEASURING AND CONTROL Opera Completion of operation Measured or set Description of servicing operation Comment tion value * numb Check the connection and condition of the 1.20.
  • Page 22: Configuration Of The Control System For Unit Start-Up

    MANDÍK CPV Installation, commissioning, and maintenance 7.3 CONFIGURATION OF THE CONTROL SYSTEM FOR UNIT START-UP The control system is completely installed from the factory and is pre-configured and tested for the specific configuration of the unit. During commissioning, it is critical to only control air output by changing the EC fan output percentage and adjusting the schedule for the "Economy"...
  • Page 23: Activities During Initial Start-Up

    MANDÍK CPV Installation, commissioning, and maintenance The following must be checked prior to initial start-up of the unit: 8.2 ACTIVITIES DURING INITIAL START-UP The fans must not be started with the shut-off dampers in the unit or the control dampers in the ductwork closed.
  • Page 24: Controlling Air Output From The Unit

    MANDÍK CPV Installation, commissioning, and maintenance 3) Starting the unit: – see Annex B. QUICK STARTING THE UNIT - WEB / POL871 HMI CONTROLLER – see Annex C. QUICK STARTING THE UNIT - POL822 ROOM UNIT 4) Controlling air output – see paragraph 8.4 5) Schedule settings –...
  • Page 25 MANDÍK CPV Installation, commissioning, and maintenance   Once differential pressure is measured [Pa], air output is calculated using the k-factor for the given fan and the equations specified in the fan sticker. Air output may also be calculated as follows: Fig 9 K-factors for open fan impellers Applies Fig 10 Measurement instrument connection.
  • Page 26: Operator Training And Handover Of The Unit

    MANDÍK CPV Installation, commissioning, and maintenance • Nominal parameters of the equipment (air output, fan motor current ratings – nameplate values) • Measuring instruments in use • Functional schematic of the equipment, including a schematic of the ductwork with dimensions and specification of components (inserted elements – attenuators, filters, etc., control dampers, tees, elbows, etc.) •...
  • Page 27: Opeation And Maintenance

    MANDÍK CPV Installation, commissioning, and maintenance training protocol for the control system, handover protocol for the unit, and unit control protocol). 9 OPEATION AND MAINTENANCE 9.1 DESCRIPTION OF THE UNIT – COMPONENTS SHUT-OFF DAMPER - EHA SHUT-OFF DAMPER - ODA ACCESS TO THE PANEL FAN - RETURN MAINS CONNECTION...
  • Page 28: Descrption Of The Unit - Control System

    MANDÍK CPV Installation, commissioning, and maintenance ETA = RETURN FROM SPACE SUP = SUPPLY TO SPACE MIXING OF SUPPLY AIR WITH RETURN AIR FRESH AIR BY-PASS Fig 12 Airflow, right-hand unit design 9.2 DESCRPTION OF THE UNIT – CONTROL SYSTEM EC1/EC2 –...
  • Page 29: General Operation And Maintenance

    MANDÍK CPV Installation, commissioning, and maintenance EC1/EC2 – supply / return EC fan M1 – supply damper actuator M2 – by-pass damper actuator M3 – return damper actuator M4 – mixing damper actuator dP1 – differential pressure switch on supply filters dP2- differential pressure switch on return filters S1 –...
  • Page 30: Maintenance And Service Intervals

    MANDÍK CPV Installation, commissioning, and maintenance ATTENTION: ALL ROTATING PARTS (FANS, ETC.) MUST HAVE STOPPED MOVING BEFORE ENTERING INTO THE EQUIPMENT! • ATTENTION: ELECTRIC HEATERS, HEAT EXCHANGERS AND HYDRAULIC SYSTEM COMPONENTS MUST BE COOLED DOWN TO AMBIENT TEMPERATURE, MEANING A MAXIMUM SURFACE TEMPERATURE OF +40°C! •...
  • Page 31 MANDÍK CPV Installation, commissioning, and maintenance SERVICING AND MAINTENANCE OPERATIONS Intervals (months) Unit in Service/rectificati Check operation operation on method Y/N * 2. FILTERS G2-F9, GREASE value from the Check the filter pressure losses. 2.01. measuring and control system Check the integrity of the filtration medium of 2.02.
  • Page 32 MANDÍK CPV Installation, commissioning, and maintenance SERVICING AND MAINTENANCE OPERATIONS Intervals (months) Unit in Service/rectificati Check operation operation on method Y/N * 4. WATER HEATER Check the integrity of the exchanger heat- repair/replaceme 4.01. transfer surface. Check the cleanness of the exchanger heat- 4.02.
  • Page 33 MANDÍK CPV Installation, commissioning, and maintenance COLD WATER COIL Inspection for damage to heat exchange surfaces 6.01. repair / replace on the heat exchanger. Inspection for cleanliness of heat exchange 6.02. clean surfaces on the heat exchanger. Inspection for leaks on the working media side of 6.03.
  • Page 34: General Operation And Maintenance Of The Unit

    MANDÍK CPV Installation, commissioning, and maintenance Unit in Intervals (months) Method of service Inspection action operatio / removal n Y / N * PLATE RECUPERATOR Inspection for damage to heat exchange 8.01. repair / replace surfaces on the heat exchanger. Inspection for cleanliness of heat exchange 8.02.
  • Page 35: Fans

    MANDÍK CPV Installation, commissioning, and maintenance Any maintenance intervals specified below are indicative only and valid for air containing normal quantities of individual pollutants. These intervals may be extended or shortened, depending on local operating conditions, the nature of the equipment, and the pollutants contained in the conveyed air.
  • Page 36 MANDÍK CPV Installation, commissioning, and maintenance Check the filer section to ensure it is clean and vacuum up any coarse dirt and debris as necessary, and then wipe up any fine dust using a damp rag. Then check the condition and seal around all filter elements.
  • Page 37: Dampers, Flexible Elements

    MANDÍK CPV Installation, commissioning, and maintenance 9.8 DAMPERS, FLEXIBLE ELEMENTS Operable damper blades must be locked to prevent spontaneous or accidental closure. Never put your fingers between the blades of an open damper as this is a serious injury hazard! Check for dirt and grime, and any damage, and inspect the movement of the damper blades, and the proper closure of the damper in particular.
  • Page 38: Condenser Coil, Direct Evaporator Coil

    MANDÍK CPV Installation, commissioning, and maintenance 9.10 CONDENSER COIL, DIRECT EVAPORATOR COIL The surface temperature of the hot water coil and media conditions when in use may exceed a safe contact temperature of 60°C. Before intervening or beginning any work in the chamber, wait for the heat exchanger and connections to cool sufficiently! Prevent contact between skin, the mucus membranes or eyes and the refrigerant when performing any work on refrigeration systems.
  • Page 39: Electric Heater

    MANDÍK CPV Installation, commissioning, and maintenance on dampers are manufactured from a material that does not require subsequent lubrication. Use a lubricating spray on the lever mechanism on those dampers with lubricated lever mechanisms. Check the condition and operation of all condensate pans, the functionality of the pan drains and the condition and functionality of the trap, and then clean and fill with water as needed.
  • Page 40 MANDÍK CPV Installation, commissioning, and maintenance Access to the terminal block is provided by removing the 5.0 mm screws from the cover using a hex key. The heater terminal block is equipped with a DIN rail for power connection terminals, SSR relays for output switching, and the operating and alarm thermostats for safe operation, see the illustration: IZU 02/2021...
  • Page 41 MANDÍK CPV Installation, commissioning, and maintenance DIN RAIL WITH TERMINALS ALARM THERMOSTAT OPERATING THERMOSTAT SSR RELAYS The operating and alarm thermostats must always be properly connected to the control system. The thermostats are wired in series and the contacts are closed at safe air temperatures inside the heater.
  • Page 42 MANDÍK CPV Installation, commissioning, and maintenance Operation of the electric heaters: ATTENTION: The heater must not be switched on until the fan is running! Airflow through the heater is required at all times, and therefore start the fan and then wait for its warm-up period until it reaches its normal working point.
  • Page 43: Annex A. Quick Fan Adjustment - Pol871 Hmi Controller

    MANDÍK CPV Installation, commissioning, and maintenance ANNEX A. QUICK FAN ADJUSTMENT - POL871 HMI CONTROLLER These instructions are the same for the web interface, the display on the controller and the POL871 HMI controller. Buttons on the POL871 HMI controller: INFO/ UP ARROW ESCAPE (BACK)
  • Page 44 MANDÍK CPV Installation, commissioning, and maintenance (press enter to confirm) Press enter on the Comfort supply / return fan row and use the arrows to adjust the fan output value [%] – use the arrows to change the value and the press enter to confirm. The Comfort [%] value is the upper speed limit on the POL822 remote control.
  • Page 45: Annex B. Quick Starting The Unit - Web / Pol871 Hmi Controller

    MANDÍK CPV Installation, commissioning, and maintenance ANNEX B. QUICK STARTING THE UNIT – WEB / POL871 HMI CONTROLLER The unit must be put in "Economy” or “Comfort” mode to start the unit. The default setting from the factor is “Off” for safety reasons. (main menu ->...
  • Page 46: Annex C. Quick Starting The Unit - Pol822 Room Unit

    MANDÍK CPV Installation, commissioning, and maintenance ANNEX C. QUICK STARTING THE UNIT – POL822 ROOM UNIT Buttons on the POL822 room unit: OPERATING MODE FAN OUTPUT SET POINT TEMPERATURE SET TEMPERATURE SET POINT POINT 1) ROOM UNIT UPDATE - When power is connected and the connection is made to the controller, the room unit updates its data for a few seconds with the Climatix controller and the “P–”...
  • Page 47 MANDÍK CPV Installation, commissioning, and maintenance If the unit is equipped with a Climatix controller with a display or POL871 HMI controller, the default operating mode is shown on the main screen: DEFAULT OPERATING MODE 3) ADJUSTING THE OPERATING MODE – The “Protection” / “Economy” / “Comfort” / “Schedule”...
  • Page 48 MANDÍK CPV Installation, commissioning, and maintenance 5) TEMPERATURE SET POINT ADJUSTMENT To change the temperature set point depending on the operating mode, use the “+” and “-” buttons to change the temperature set point. TEMPERATURE ADJUSTMENT DIFFERENCE FROM DEFAULT VALUE LOWER TEMPERATURE RAISE TEMPERATURE IZU 02/2021...
  • Page 49: Annex D. Mains Connection - Hot Water Heating

    MANDÍK CPV Installation, commissioning, and maintenance ANNEX D. MAINS CONNECTION – HOT WATER HEATING IZU 02/2021 MANDÍK, a.s., www.mandik.cz...
  • Page 50: Annex E. Mains Connection - Electric Heating

    MANDÍK CPV Installation, commissioning, and maintenance ANNEX E. MAINS CONNECTION – ELECTRIC HEATING IZU 02/2021 MANDÍK, a.s., www.mandik.cz...
  • Page 51: Annex F. Peripherals - Co2 Sensor, Pol822 Room Unit, Piping Temperature Sensor

    MANDÍK CPV Installation, commissioning, and maintenance ANNEX F. PERIPHERALS – CO2 SENSOR, POL822 ROOM UNIT, PIPING TEMPERATURE SENSOR IZU 02/2021 MANDÍK, a.s., www.mandik.cz...