General Information Service Contact For local maintenance and service information, please contact your nearest Authorized Service Representative. Service inquiries may be directed to technical support at: OptiPure 101 South Gary Avenue, Suite A Roselle, IL 60172 USA Phone #: 972.881.9797 E-mail correspondence to: techsupport@optipure.net Completed BWS175 Environmental Conditions...
Installation Requirements Operating a system on water supplies outside Drain of the parameters listed below may lead to A drain should be located within 10 feet of premature membrane failure. This product is the system. Drain must allow a minimum flow for commercial use only and must be installed of 2 gals./min.
Page 4
BWS175 Installation Diagram Water Processor Plumbing should be performed in accordance with local codes. Blending Valve IMPORTANT - PROTECT PROCESSOR AND TANK FROM THE ELEMENTS. DO NOT INSTALL IN DIRECT SUNLIGHT OR WHERE EXPOSED TO FREEZING TEMPERATURES OR RAIN. User-Supplied Feed Water Valve Feed Water Line -...
Page 5
Step 1 Mount Processor Attach the system with 2 screws (user supplied) through the attachment keyholes shown Mount the system with the Pre-Installed Drain Line below. Use anchors or attach directly to studs. Be sure to allow at least 3” clearance (1/4”...
Page 6
Install Membrane Install the Pre-Filter Step 2a Step 3 Insert and lock the CTO-Q10 Cartridge into the Insert the AMS-QT15 Membrane into the center Pre-Filter Head as shown. head and rotate it to the right 1/4 turn to lock. NOTE: The pre-filter head has a built-in shut off valve.
Page 7
Make Drain Connection Make Feed Connections Install Tank Valve and Tee Assembly Step 4 Step 5a Route and connect the loose end of 1/4” black Install the Feedwater Adapter (from the (DRAIN) tubing coming from Permeate Pump on installation kit) into the user-supplied 1/2” processor to a suitable drain;...
Page 8
Make Optimized Water Connections Follow instructions below and proceed to next step. Step 7a Step 7b Step 7a Step 7a Step 7b Do not connect to equipment at this Connect a piece of 3/8” blue tubing to the The remaining connection at the Tank Tee is the time.
Page 9
Make TDS Monitor Connection Installing the TDS monitor. Step 7c Step 7c Install TDS Monitor next to the RO processor using sticky tape with Velcro (supplied with monitor). Connect TDS Probe to 1/4" tee fitting located right before Optimized Water to Storage Tank fitting connection.
Flush the System Step 8 Step 9a Step 10 Temporarily route the 3/8” blue tube from the Open the Feed Valve. Allow water to flow to Ensure Bypass Valve is CLOSED. Optimized Water Outlet on the Storage Tank drain until all air is purged from the system. Step 9b Line to a drain or sink.
Page 11
Set Blending Valve & Connect to Equipment Step 11 Step 11b Step 11a Set blending valve to desired optimized Make the connection to the equipment. water TDS: Connect ONLY the treated/steam water connection at the equipment. Do not connect to Route and secure the 3/8”...
Page 12
Place in Service Quick Tank Fill Step 13 If a water supply to downstream Simply OPEN the Bypass Valve and un-filtered water will flow directly into the storage tank. equipment is immediately When the tank is full, or a desired level is needed, the storage tank can be reached, CLOSE the Bypass Valve.
Operation SHUT OFF WATER TO SYSTEM Step 1 Step 2 The system operates normally when water, under pressure, is supplied to the system. Typical filter replacement is every 6 months (CTOS-Q10 and ILMA-10.14). Typical Close Feed Water Supply Valve. Close the Storage Tank Valve. membrane replacement is every 24 months (AMS-QT10) or less, based on water quality.