gas
DIRECT VENT — Sidewall with separate pipes
All vent pipes and air inlets must terminate at the same
height to avoid possibility of severe personal injury, death
or substantial property damage.
2. Place wall penetrations to obtain minimum clearances shown in
Figure 28 for U. S. installations. For Canadian installations, provide
clearances required by Natural Gas and Propane Installation Code,
CAN/CSA B149.1 or B149.2 and a ULC S636 compliant vent kit.
3. The air inlet of a Evergreen
tion. It is not classified as a forced air intake with regard to spacing
from adjacent boiler vents.
Prepare wall penetrations
1. Air pipe penetration:
a. Cut a hole for the air pipe. Size the air pipe hole as close as
desired to the air pipe outside diameter.
2. Vent pipe penetration:
a. Cut a hole for the vent pipe. For either combustible or non-
combustible construction, size the vent pipe hole at least 0.4"
larger than the vent pipe diameter.
b. Insert a galvanized metal thimble in the vent pipe hole as
shown in Figure 29.
3. Use the provided paper template for correct location of hole centers.
4. Use of a sidewall termination plate is REQUIRED.
a. Kits for several vent sizes are available from Weil-McLain.
See "VENT/AIR PARTS AND KITS" on page 117.
b. Plate may be field fabricated from corrosion resistant material
of sufficient strength. Plate must allow venting to maintain
minimum clearance to combustibles.
Ensure that the plate material is strong enough to prevent
the termination from being pushed inward if struck or
pushed from the outside.
5.
Follow all local codes for isolation of vent pipe when passing
through floors or walls.
6. Seal exterior openings thoroughly with exterior caulk.
Termination and fittings
1. Prepare the vent termination elbow and the air termination elbow
by inserting bird screens. (See Figure 27, page 25.) Bird screens
must be purchased separately. See the parts list at the end of this
manual for part numbers.
2. When completed, the air termination coupling must be oriented
at least 12 inches below the vent termination and at least 12 inches
above grade or snow line as shown in Figure 27, page 25.
3. Orient the vent termination elbow directly outward as shown in
Figure 27, page 25.
4. Maintain the required dimensions of the finished termination
piping as shown in Figure 27, page 25.
5. For multiple boiler terminations, see Figure 28.
6. Do not extend exposed vent pipe outside of building more than shown
in this document. Condensate could freeze and block vent pipe.
If extending the vent and air pipes out from the wall,
install a coupling on each pipe. Mount the piping with
the coupling flush with the outer plate.
Wall penetration thickness between 0" to 24".
– 26 –
-
fired water boiler
See notices on previous page.
®
boiler is part of a direct vent connec-
— 220/299/300/399 Boiler Manual
Figure 28
Figure 29
1 Air piping.
2 Vent piping.
3 Sidewall termination plates: for 4" PVC,
use plates supplied with boiler in W-M
vent/air plate kit; for 4" AL29-4C or 3" PVC,
purchase optional sidewall separate pipes
plate kit.
Multiple separate pipes sidewall terminations
— maintain vertical spacing between vent and
air fittings shown in Figure 27, page 25.
Sidewall termination assembly — using
separate pipes
4 Galvanized thimble, by in-
staller.
5 Bird screen, by installer.
6 Air inlet elbow.
7 Elbow.
8 Nipple.
9 Elbow (vent termination).
Part number 550-100-131/0120
(continued)

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Evergreen evg 299Evergreen evg 300Evergreen evg 399

Table of Contents