Fax: (480) 951-6879 Revised: 3/13/18 Below is a parts list describing all of the items included with the Model E-500 System. You may also wish to refer to the dimensional diagram shown on pages 22-24. Before beginning assembly and installation, please make sure that you have all items included on the list. If any parts are missing or damaged, please contact Nexus 21 using the contact info shown at the top of this page.
Page 5
Parts List Continued Hardware 1. Eight (8) -- 5 x 14mm FHMS (Flat Head Machine Screw) 2. Four (4) – Set Screws 3. Four (4) – Fine Adjustment Screws 4. Sixteen (16) -- #8 – ½” FHWS (Flat Head Wood Screw) 5.
Page 6
Nexus 21 disclaims any liability for modifications, improper installations, or installations over the specified weight range. Nexus 21 will not be liable for any damages arising out of the use of, or inability to use, Nexus 21 products. Nexus 21 bears no responsibility for incidental or consequential damages. This includes, but is not limited to, any labor charges for the servicing of Nexus 21 products performed by anyone other than Nexus 21.
Page 7
Page 21. TIP: Planning to integrate the TV Lift with your UNIVERSAL REMOTE CONTROL? The RF version of the Nexus 21 controls won’t do it. Switch to IR. These are the parts included with RF controls: Backup Switch...
Page 8
- All electrical hookups must be installed per authorized building codes All information provided below is located within the Model E-500-Dimensional-Drawing for more information pertaining to the specifications listed below, refer to the dimensional drawing located at the end of this manual.
Table of Contents Before You Begin Installing the Actuation System Projector Mounting Ceiling Panel Attachment Projector Adjustment Setting a Travel Limit Dimensional Drawing Control System Integration Info...
• Phillips Bit or Screw Driver Step 1: Connect the Power Cord for the E-500 to an Outlet or Receptacle located above the Installation Bracket. Step 2: Remove the Left Cable Terminal Cover by removing both of the Phillips Screws.
Page 11
Step 3: Pass all AV, Integration, and Power Cables for Projector and E-500 Lift System through Cable Outlet inside the terminal. Note: If you purchased the lift with the CSI Kit, make sure to manage the cable for Contact Closure or the IR Receiver as well.
Installing the Actuation System For these steps you will need the following: • E-500 Actuation System • (Pre-Framed) Installation Bracket • (4) Fine Adjustment Screws • 3mm Allen Key or T-Handle (Provided) Snap Feature Front of System Step 6: Take a moment to locate the Snape Feature on each side of the Actuation System. Now press and snap the Actuation System into place within the Installation Bracket.
Page 13
Step 8: Locate the Control Panel at the front of the system then, using a 3mm T-Handle or Allen Key, remove both of the Control Panel Screws to lower and expose the Wired Backup Switch. Step 9: Using the Wired Backup Switch, run Crossmember into the DOWN position.
Projector Mounting For these steps you will need the following: • Universal Adjustment Bracket • Universal Mounting Bracket • Carrier Shroud • Projector • Projector Mounting Hardware (Not Included) • (1) M8 Nyloc Nut (Already Attached) • (4) 5 x 14mm FHMS Screws •...
Page 15
Step 12: Slide the Adjustment Bracket onto the Mounting Bracket then fasten the two together, using (1) 8mm Nyloc Nut and Flat Washer with a 13mm Crescent Wrench. Note: Ensure the front of the Projector sits behind the locating flange on the Adjustment Bracket before completely fastening the two together.
Page 16
Step 13: Press and slide the Shoulder Bolts, located on the Top of the Mounting Assembly, in to the Keyed Holes of the Crossmember inside of the Actuation System. Reference the Arrows in the image below for the direction. Important Note: Slowly remove pressure on the Projector to ensure the Mounting Assembly is within the keyed holes.
Page 17
Step 15: Connect and manage any cables for integration or the projector and feed any excess cable back up and through the Left Cable Terminal. Step 16: Press and slide the Carrier Shroud into the L shaped slots located on the left and right side of the Crossmember then fasten the Carrier Shroud to the Crossmember using (4) 5 x 14mm FHMS Screws, (2) per side.
Ceiling Panel Attachment For these steps you will need the following: • Interface Plate • Trim Ring Rear • Ceiling Panel • (9) Wood Screws • (4) Set Screws • (4) 5 x 14mm FHMS Screws Front Step 17: Center and attach the Ceiling Panel to the Interface Plate using the provided Wood Screws or appropriate hardware/adhesive.
Page 19
Step 19: Using your remote, run the E-500 into the UP position to measure the flushness of the Ceiling Panel relative to the surrounding ceiling. Note: If adjustments are needed, run the system down, remove the Interface Plate then tighten the Fine Adjustment Screws to move the Ceiling Panel UP, and loosen the Fine Adjustment Screws to move the system DOWN.
Projector Adjustment Step: Run the system down to expose the projector. Step 22: Adjust Roll, Pitch, and for Projector by placing a 3mm T-Handle or 3mm Allen Bit through the slotted holes on the underside of the Carrier Shroud. Note: Roll is to the Right, Pitch is in the Center, and...
4. Fully retract the system by pressing the RETRACT button then extend it again to test the position. About Upper Limits: The Upper Limit for the E-500 is mechanically limited to a maximum of 1.25” via the Fine Adjustment Screws. If you are having an issue where further adjustment is required, contact Technical Support at 480-275-8613...