Operations and Maintenance Instruction
1 Transport
Upon receipt, please check the valve with eventual equipment (Actuator, etc.) for any
damage which may have occurred during shipment.
When shipping the valve, it should be made sure that it is secured on a pallet
avoiding it to slide or fall over during transport. If transporting or lifting the valve with
a rope or hook, it should be attached in a way avoiding that the valve accidentally
slips sidewards.
Do not use any lifting tackle (rope, chain, sling..) through the open valve.
2 Safety indication
If operating temperatures are > 50 ° C, protection against accidental contact and
spray -risk has to be applied.
Connecting the electrical- or electro pneumatic- connections has to be carried out by
authorized professional staff only.
When operating (on - off cycling) the valve while not flanged in line, do never attempt
to touch the inside of the ball (bore).
In case of toxic, corrosive and explosive fluids, respective guidelines need to be
followed. When disassembling the valve, make sure that possible contaminated
residues are disposed off as hazardous waste.
3 Installation
Pipeline
Install the valve into the line so that the arrow on the valve body points into the flow
direction. Should the actuator be too heavy, separate bear up support may be
required.
Install the valve without strain and tension. Additional forces by the pipeline are not
allowed (see DIN 2502).
The ball valve should be flanged in by using standard gaskets.
Make sure that the gaskets are not damaging the ceramic inlet and outlet
liners of the valve.
Dok.-No.
BA-KST 10-02.2
CERAVALVE
Ball Valve – KST
Page 1 of 6

Advertisement

loading

Summary of Contents for Cera System CeraValve KST Series

  • Page 1 +49 (0) 3 66 01 9 19-0 +49 (0) 3 66 01 9 19-77 eMail info@cerasystem.de Operations and Maintenance Instruction 1 Transport Upon receipt, please check the valve with eventual equipment (Actuator, etc.) for any damage which may have occurred during shipment. When shipping the valve, it should be made sure that it is secured on a pallet avoiding it to slide or fall over during transport.
  • Page 2 +49 (0) 3 66 01 9 19-0 +49 (0) 3 66 01 9 19-77 eMail info@cerasystem.de 6 Nm M 12 47 Nm M 24 410 Nm ⇒ ⇒ ⇒ Bolting torque 13 Nm M 16 118 Nm M 27 605 Nm ⇒...
  • Page 3 +49 (0) 3 66 01 9 19-0 +49 (0) 3 66 01 9 19-77 eMail info@cerasystem.de More information on the ceramic material used in a particular job number can be found in the technical specification of the job number The valve is only to be used in specifically determined pressure-, temperature- and fluid conditions.
  • Page 4 +49 (0) 3 66 01 9 19-0 +49 (0) 3 66 01 9 19-77 eMail info@cerasystem.de 5.1 Testing points in case of malfunction Malfunction Possible cause Remedy Valve does not Actuator supply air too low Check air supply, increase it to max move while respecting the max.
  • Page 5 +49 (0) 3 66 01 9 19-0 +49 (0) 3 66 01 9 19-77 eMail info@cerasystem.de 5.2 Disassembly Remove actuator Turn ball in closed position, loosen Allen screws, remove bonnet flange and pull stem out Put valve on its downstream flange, loosen hexagon nut and loosen upstream flange from body Remove upstream seat from the socket If the wear sleeves are eroded or damaged, remove them with the help of a...
  • Page 6 +49 (0) 3 66 01 9 19-0 +49 (0) 3 66 01 9 19-77 eMail info@cerasystem.de Put the socket on the seat in a way that the socket bore (stem passage) is aligned to the flat surface of the flange Insert o-ring into the downstream flange and put the body on it.