  • Page 1 RoomMaster ABR-2 Commissioning...
  • Page 2: Table Of Contents

    RoomMaster ABR-2 COMMISSIONING Content GENERAL Locking of operating mode keys ......................3 Control panel ...............................3 Function of operating mode keys, operating menu ................3 Activation of setting keys ..........................4 Locking of setting keys ..........................4 Setting menu structure ..........................4 Function of setting keys ..........................4 START-UP Factory settings on delivery ........................5...
  • Page 3: Locking Of Operating Mode Keys

    RoomMaster ABR-2 COMMISSIONING Locking and function of operating mode keys Locking of operating mode keys Control panel The operating mode keys “Overtime operation“, “Ven- The control panel is equipped with a 2 x 20 character tilation“ and “Stop“ can be blocked individually, if re- window of the LED backlight type, where the operating quired;...
  • Page 4: Activation Of Setting Keys

    RoomMaster ABR-2 COMMISSIONING Activation, locking and function of setting keys Activation of setting keys Function of setting keys Press down the setting keys Next. Used to move to the next window at the simultaneously for 5 seconds. same menu level.
  • Page 5: Factory Settings On Delivery

    RoomMaster ABR-2 COMMISSIONING Commissioning - start-up Factory settings on delivery Example: Changing standard flow Self-test and Calibration are always carried out prior to The standard flow must be changed from 200 l/s to 220 delivery from the factory. Setting and checking the func- l/s.
  • Page 6: Program Version

    RoomMaster ABR-2 COMMISSIONING Commissioning - start-up Program version Checking prior to commissioning These instructions are applicable to program version 1.0. In order to obtain a functionally reliable system, a simple Information about the type of program version in a unit check is necessary in conjunction with commissioning a can be found in window 77 and/or on the control card.
  • Page 7: Procedure - Setting

    RoomMaster ABR-2 COMMISSIONING Procedure - setting Setting temperature regulation and desired temperature value The setting ranges are shown after the current window. The default value is underlined. 1. Press the keys at the same time for approx. 5 seconds. Window 10 is displayed...
  • Page 8: Setting Of Exhaust Air Flow, Standard And Reduced Flow And Supply Air/Exhaust Air Flow Ratio

    RoomMaster ABR-2 COMMISSIONING Procedure - setting Setting of exhaust air flow, standard and reduced flow and supply air/exhaust air flow ratio The setting ranges are shown after the current window. The default value is underlined. 1. Press the keys at the same time for approx. 5 seconds. Window 10 is displayed...
  • Page 9: Setting Operating Times And Operating Mode In Weekly Rhythm (Window 30)

    RoomMaster ABR-2 COMMISSIONING Procedure - setting Setting operating times and operating mode in weekly rhythm (Window 30) The setting ranges are shown after the current window. The default value is underlined. 1. Press the keys at the same time for approx. 5 seconds. Window 10 is displayed Set desired value 2.
  • Page 10: Setting Operating Times And Operating Mode In Weekly Rhythm (Window 40)

    RoomMaster ABR-2 COMMISSIONING Procedure - setting Setting operating times and operating mode in weekly rhythm (Window 40) The setting ranges are shown after the current window. The default value is underlined. 1. Press the keys at the same time for approx. 5 seconds. Window 10 is displayed Set desired value 2.
  • Page 11: Setting Clock (Window 50)

    RoomMaster ABR-2 COMMISSIONING Procedure - setting Setting clock (Window 50) 1. Press the keys at the same time for approx. 5 seconds. Window 10 is displayed Set desired value 2. Press the key (4 times) until window 50 is displayed...
  • Page 12: Activation Of Summer Night-Time Cooling (Window 60)

    RoomMaster ABR-2 COMMISSIONING Procedure - setting Activation of summer night-time cooling (Window 60) The setting ranges are shown after the current window. The default value is underlined 1. Press the keys at the same time for approx. 5 seconds. Window 10 is displayed...
  • Page 13: Calibration Of Unit (Window 71B)

    RoomMaster ABR-2 COMMISSIONING Procedure - setting Calibration of unit (Window 71b) 1. Press the keys at the same time for approx. 5 seconds. Window 10 is displayed Set desired value 70 Test /Default value 2. Press the key (6 times) until window 70 is displayed...
  • Page 14: Reset Default Values (Window 71C)

    RoomMaster ABR-2 COMMISSIONING Procedure - setting Reset default values (Window 71c) 1. Press the keys at the same time for approx. 5 seconds. Window 10 is displayed Set desired value 70 Test /Default value 2. Press the key (6 times) until window 70 is displayed...
  • Page 15: Activation (Blocking) Of Operating Mode Keys

    RoomMaster ABR-2 COMMISSIONING Procedure - setting Activation (blocking) of operating mode keys STOP 1. Press the keys at the same time for approx. 5 seconds. Window 10 is displayed Set desired value 70 Test /Default value 2. Press the key (6 times) until window 70 is displayed...
  • Page 16: Program Version (Window 77)

    RoomMaster ABR-2 COMMISSIONING Procedure - setting Program version (Window 77) 1. Press the keys at the same time for approx. 5 seconds. Window 10 is displayed Set desired value 70 Test /Default value 2. Press th key (6 times) until window 70 is displayed...
  • Page 17: Alarm And Fault-Finding

    RoomMaster ABR-2 COMMISSIONING Procedure - setting Alarm and fault-finding The alarm message is displayed in the window in clear text at the same time as a red LED flashes on the control panel. Alarm message Operation Cause Remedy Unit stops Power supply to motor interrupted.
  • Page 18: Menu Structure

    RoomMaster ABR-2 COMMISSIONING Procedure - setting Menu Structure Fläkt Woods 8061 GB 2009.05 Specifications are subject to alteration without further notice.
  • Page 19: List Of Parameters

    RoomMaster ABR-2 COMMISSIONING Procedure - setting List of parameters Wind. Description Default Wind. Description Default value setting value setting Air flow Set time/activity Saturday Main menu Set desired value Change-over time 1 Saturday 8:00 Standard flow: exhaust air 200 l/s...