Installation Instructions

IMPORTANT WALL TRACK SAFETY NOTICE

• To use the X1 requires the installation of the provided Wall Track. *
• Do not commence installation until you have read and understood the instructions and
warnings contained in this installation sheet.
• Professional installation is highly recommended.
• Improper installation or use of the X1 or Wall Track may cause damage or serious injury.
• Be aware of electrical wiring before any drilling or screwing into walls.
• Only mount the Wall Track to a structural wall or structural stud. Examples of structural
walls include:
o Solid walls (brick, masonry) or
o Plaster walls with approved structural stud
• If mounting to timber or steel wall studs, make sure that the mounting screws are anchored
into the centre of the studs. Use of a stud finder is highly recommended.
• The wall must be flat. If the Wall Track is not installed onto a flat surface then it will be
difficult to use the X1 properly.
• Due to forces experienced by the Wall Track when the X1 is in use, each screw must be
installed firm and tight.
• Regularly check each screw is firm and tight in Wall Track. Tighten each Wall Track screw
as required.
• Do not conduct the Wall Track installation process within 5m (16ft) of others as this will
present a safety risk.
• Any personal or property damage or injury caused by a lack of personal care or not
following the instructions fully is not covered by the warranty.
• Do not place the X1 or the Wall Track in the following environments:
o An area of high humidity such as a bathroom
o Near any heat source such as stoves and other devices that produce heat
o Near kitchen counters
o An area exposed to wind or rain
o Do not install in excessively dusty places
*Professional installation is highly recommended

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the X1 Wall Track and is the answer not in the manual?

Questions and answers

Summary of Contents for adapt X1 Wall Track

  • Page 1 X1 Wall Track Installation Instructions IMPORTANT WALL TRACK SAFETY NOTICE • To use the X1 requires the installation of the provided Wall Track. * • Do not commence installation until you have read and understood the instructions and warnings contained in this installation sheet.
  • Page 2 Required Tools (not supplied with X1): • Power Drill • Stud finder (not required for brick or masonry wall) • Phillips Head Screw Driver Bit No 2 • Spirit Level Included Parts (supplied with X1): Image: a. Wall Track (3 Pieces) b.
  • Page 3 WALL TRACK INSTALLATION GUIDE Please note – The Wall Track installation guide is provided to support professional installation of the wall track. A professional installer must satisfy themselves that the Wall Track has been secured appropriately. Step 1 – Assemble the Wall Track: a.
  • Page 4 Step 2 - Find the right location: a. A minimum of 0.5m (20in) of side space and 2.0m (6ft 7in) of floor space around the X1 for training (see Image 4) b. A structural wall or structural stud (as described above) – To be clear; if you are installing onto a plaster wall you must install screws into the wall stud c.
  • Page 5 Step 3 - Determine the Wall Track position: a. Place the Wall Track on the selected wall. Please ensure that the grub screws have been tightened to keep the track together b. The bottom of the Wall Track should be 30cm (12in) from the floor. Ensure that it is not lower than 30cm from the floor (see Image 5) c.
  • Page 6 Step 4 - Solid Wall (masonry / brick / concrete) Install Instructions: a. Before install ensure that you have found the right location (step 2) and positioned the Wall Track correctly (step 3) b. If you are drilling into a brick or masonry wall use the supplied masonry drill bit. Ensure you do not drill into the mortar as this will not be strong enough.
  • Page 7 Step 4 - Plaster Wall (with steel studs) Install Instructions: a. Before install ensure that you have found the right location (step 2) and positioned the Wall Track correctly (step 3) b. Use the stud finder to find the stud c.
  • Page 8 Step 4 - Plaster Wall (with timber studs) Install Instructions: a. Before install ensure that you have found the right location (step 2) and positioned the Wall Track correctly (step 3) b. Use the stud finder to find the stud c.

Table of Contents