Page 3
Regulatory Prior to installation, it is necessary to find a suitable site indoors (this product should always be installed indoors). It is assumed that the installer has required certifications and required permits. The Installer must follow electrical standards and AHJ requirements. All National and local Electrical codes apply.
Table of Contents Introduction Package Contents Installation Mounting the Control Panel Case Power Supply Board Overview Setup the FPO250 Power Supply Board Setup the FPO75 Power Supply Board Setup the D8P Power Supply Boards Setup the C8 Power Supply Boards Install the ACM Embedded Controller and V100 Subpanels Configure and Wire Data Configure and Wire Power...
Introduction The Access Control Manager (ACM) Embedded Controller from Avigilon is an all-in-one security management application and controller. The ACM Embedded Controller is a controller embedded with the ACM Embedded Controller application to provide a flexible and scalable platform for an economic and high performance access control system.
Installation Before you install the ACM Embedded Controller, read through this entire document. Refer to the checklist at the end of this document and gather the required information before proceeding with these instructions. CAUTION — The controllers and interface panels are sensitive to Electrostatic Discharges (ESD). Observe precautions while handling the circuit board assembly by using proper grounding straps and handling precautions at all times.
Mounting the Control Panel Case Follow the steps below to mount the control panel case. 1. At the installation site, remove the control panel case from the LifeSafety Power FlexPower box. 2. Find two studs in the wall where the enclosure should be installed. NOTE: In a finished setup, the enclosure and contents together weighs 22.2kg (49lb).
Page 8
7. Setup the high voltage junction box (or equivalent), as required. Attach an appropriate cable gland to the junction box and feed the five AC wires through (two white, two black, one ground). KEY: 1 is a sample high voltage junction box, while 2 and 3 are sample cable glands. CAUTION —...
Setup the FPO250 Power Supply Board Follow the steps below to setup the FPO250 power supply board: 1. Either: For 120V input, leave JP1 intact. For 230V input, cut JP1. CAUTION: Failure to cut this jumper when using the FPO with a 230VAC input will result in damage to the system and will void the warranty.
Page 11
3. Connect the inputs on the FAI (Fire Alarm Input) to the building’s fire alarm system, as required. See the FPO Quick Start Manual (page 3 – FAI Input Usage) for more detail. Further information is available at: http://lifesafetypower.com/docs/im_fpo.pdf. 4. Either: If a backup battery is used –...
Setup the FPO75 Power Supply Board Follow the steps below to setup the FPO75 power supply board: 1. Either: For 120V input, leave JP1 intact. For 230V input, cut JP1. CAUTION — Failure to cut this jumper when using the FPO with a 230VAC input will result in damage to the system and will void the warranty.
3. Either: If a backup battery is used – move the jumper to position 1, as shown below. If no backup battery used – move the jumper to position 2. NOTE: If using battery backup then a separate enclosure is required for the batteries due to space limitations in this enclosure.
Setup the C8 Power Supply Boards Set the jumpers properly for your installation on both C8 boards as outlined below: Jumpers Position Either: Red - 1A to 8A (Zone FAI enabled) 1. FAI enabled 2. FAI disabled Either: Blue - 1B to 8B (Input Invert) 1.
Page 15
Jumpers Position Either: Black - 1E to 8E (Dry Output Selection) 1. Relay Contact Output 2. Voltage Output Either: White - 1F to 8F (Output Invert) 1. NO - voltage when input is activated 2. NC - voltage when input is deactivated See the C4/C8 Quick Start Manual or C4/C4P C8/C8P Installation Manual for more detail (available at http://www.lifesafetypower.com/docs/im_c4c8.pdf).
V100 Install the ACM Embedded Controller and V100 subpanels as shown below: 1. Unbox the Avigilon ACM Embedded Controller and V100 subpanels. 2. Locate 12 screws and 24 Hex nuts from the accessory bag in the FlexPower box. 3. Verify battery jumper (Batt) on the ACM Embedded Controller has been set to ON position.
Page 17
4. Mount the ACM Embedded Controller and the Address 0 and Address 1 V100's as shown below (the arrows show screws). Embedded Controller V100 Address 0 V100 Address 1 5. Mount the other V100 subpanels on the pre-installed studs mounted on the door as shown below (the arrow in the picture below show Hex nuts that will connect to the studs).
Configure and Wire Data Follow the steps below to configure and wire the ACM Embedded Controller: 1. Set Port 1 terminating jumper (P6 Port 1 TERM Resistor) to IN position. 2. Verify Port 2, 3, 4 terminating jumpers are in the OUT position. 3.
Page 19
6. On the FPO250’s ACFLT terminal block: Wire C to AC Fail + (22AWG). Wire NO to AC Fail - (22AWG). Tamper Batt +12-24VDC (Input 5) Fail Fail (Input 6) (Input 7) FPO250 Embedded Controller FAI INPUT SYS FLT AC FLT C NC NO NC NO 7.
Page 20
10. Starting from the ACM Embedded Controller's P3\RS-485 Port1 terminal block, connect the A, B, and Shield connections to the V100 P9\RS-485 subpanel A, B, and Shield connections as shown below (22 AWG). V100 V100 (Addr 7) (Addr 6) RS-485 Shield Port 1 RS-485 In...
Configure and Wire Power Do the following for each V100 (except where indicated otherwise) in order for the ACM Embedded Controller application to not show an alarm: 1. Place a jumper across Tamper + and - (22AWG). 2. Place a jumper across AC Fail + and - (22AWG) for Addresses 1 to 7 only. 3.
Page 23
7. Connect cabling from the R10 readers at the door to the appropriate P1/P4 reader connection on the V100. 8. Wire the V100s’ strike relay outputs (NO & C or C & NC) to the C8 board inputs as shown below: NOTE: Shown below is the recommended configuration.
Page 24
Using the default C8 configuration: V100 Strike Relay configuration Locked Unlocked NO/C (recommended) C/NC (alternate option) If deviation from the default configuration is desired, see the C4/C8 Quick Start Manual or C4/C4P C8/C8P Installation Manual for more detail (available at http://www.lifesafetypower.com/docs/im_c4c8.pdf). 9.
Power On Follow the steps below to power on and verify the installation: Note: Once connected, the card readers may beep – this will go away once the ACM Embedded Controller has been configured. 1. Connect the High Voltage AC input to the FPO power supply. CAUTION —...
Accessing ACM Embedded Controller Application for the First Time After the controller has been installed, you need to access the ACM Embedded Controller application to complete the system configuration. You can access the application by using the controller hostname or virtual port. By Virtual Port By default, every controller can be accessed from this IP address: 169.254.242.121 To perform this procedure, you must use a Windows computer with a web browser and a network port.
The following equipment is provided: Tool Required/Recommended/Optional One AC-LSP-16DR-HID-LCK LifeSafety Power 16 door □ HID dual voltage integrated power system (supplied in Required a separate shipping box) One Avigilon AC-HID-ACMEC V1000 ACM Embedded □ Required Controller □ Eight AC-HID-VERTX-V100 reader interface modules Required □...
Page 28
The following equipment is also required: Tool Required/Recommended/Optional One Plywood board 4’ x 4’ (½” to ¾” thick). Fire rated □ Required recommended. □ Six Wood screws (sizing as required) Required □ Six Drywall anchors (sizing as required) Required □ High voltage wiring (sizing as required) Required □...
Need help?
Do you have a question about the AC-ACMEC-KIT16 and is the answer not in the manual?
Questions and answers