Download Print this page

Charles 360-80 Test Procedure

Intelligent channel bank turn-up and acceptance

Advertisement

360-80 Intelligent Channel Bank Turn-Up and
CONTENTS
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
e2006 Charles Industries Ltd.
All rights reserved. Printed in United States of America.
The availability of features and technical specifications herein subject to change without notice.
Telecommunications Group
Acceptance Test Procedure
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Section 360-080-102
Equipment Issue 2
First Printing, August 2006
PAGE
Page 1 of 9
2
2
2
3
5
5
7
9

Advertisement

loading

Summary of Contents for Charles 360-80

  • Page 1: Table Of Contents

    Section 360-080-102 Equipment Issue 2 Telecommunications Group First Printing, August 2006 360-80 Intelligent Channel Bank Turn-Up and Acceptance Test Procedure CONTENTS PAGE Part 1. GENERAL ................
  • Page 2: Part 1. General

    Section 360-080-102 GENERAL Document Purpose This document provides turn up and acceptance test procedures for the 360-80 Intelligent Channel Bank (ICB). VERIFYING ELECTRICAL CONNECTIONS Initial Installation Notes Step Action Shelf must already be mounted per documentation. Unit must already be wired for power from a fuse panel. Power should not be applied at this time.
  • Page 3: Part 4. Control Verification

    Section 360-080-102 Step Action Verification Insert the T1-S into the ICB. Do NOT connect the The green LED on the T1-S should be lit, indicat- T1 to J1 at the rear of the T1-S. ing that the T1-S is powered. When first plugged in, the AR, AY, TP and LP LEDs on the front panel of the T1-S will light and then extinguish.
  • Page 4 Section 360-080-102 Step Action System Response If the Network Management System (NMS) Soft- The system is automatically restarted and control ware will be used, do the following. Otherwise, verification is ended. skip to the next step. Select the IP Address option Configure the IP Address and network for the controlling PC Select the Apply Changes button.
  • Page 5: Part 5. Verifying System Alarms

    Section 360-080-102 Step Action System Response Once the trunk processing LED has extinguished, The LP LED should turn on and the following infor- select Status " Retrieve T1 Parameters. mation should be displayed: Status of the Incoming Primary T1 Line Card Type: Operation Mode: Normal Mode Timing Source: Internal Timing...
  • Page 6 Section 360-080-102 Step Action System Response For a full-size FXS, connect a test cable from a telephone to one of the TIP/RING pairs on the rear connector. For a half-size FXS, connect the test cable from a telephone to the front connector. Place the telephone off-hook and verify that the appropriate chassis slot LED lights only when the telephone is off-hook.
  • Page 7: Part 7. Data Card Acceptance Tests

    Section 360-080-102 DATA CARD ACCEPTANCE TESTS Use the following procedures to verify data cards after all the previous T1 unit acceptance testing (electrical con- nections, system turn-up, control verification and system alarms) has been completed. ISDN Card Acceptance Test Step Action System Response Make sure that the ICB is turned up and operating.
  • Page 8 Section 360-080-102 Step Action System Response Connect the appropriate digital data cable to a DTE test set should show a pattern sync and no bit DTE test set or equivalent. The test set should be errors should occur. capable of performing Bert tests. Note: RTS must be enabled on the external test set or FORCE RTS on the external DSU...
  • Page 9: Part 8. Technical Assistance

    For both the user and password enter, admin. Enter the following: Verify that the ping is returned. ip ping 192.168.0.1 TECHNICAL ASSISTANCE If technical assistance is required, contact Charles Industries’ Technical Services Center at: 847-806-8500 847-806-8556 (FAX) 800-607-8500 techserv@charlesindustries.com (e-mail)