Chapter 13
Verifying settings by secondary
injection
Note!
Please observe the measuring accuracy of the terminal, the test equipment and the angular ac-
curacy for both of them.
Note!
Please consider the configured logic from the function block to the output contacts when mea-
suring the operate time.