Setup/Filling Procedure ……………..………………………………………………………………………………………………6 Calibration of Temperature Probe.…………………………………………………………………………………………….10 Alarms and Definitions………………………………………………………………………………………………………………11 Contact Information………………………………………………………………………………………………………………….11 NOTE: MVE Fusion cryogen freezer should be installed by Chart Personal or an authorized MVE Distributor per the MVE Fusion Technical Manual, PN 20994124. 2 – 21205647 B...
Display / Control Panel Table 1: Front Panel Identification Front Panel MVE FUSION Graphical User Interface (GUI) Temp A and Liquid Nitrogen (LN2) % with Timeline Graph. Display A Liquid Crystal Display (LCD) shows the value of all the current conditions including Temperature and LN2 level.
MVE FUSION Quick Reference Guide Bottom Panel / Electrical / Physical Connections Temp Probe Global Alarm Contacts (These connections monitor All Alarms) Service Port Service Port Input Power Main Power Switch Battery Backup Switch 4 – 21205647 B...
“flash-off” rate during filling and to maximize the cryogenic valve life. 3. The transfer hose can be insulated to minimized liquid transfer losses. 4. Connect the other end of the transfer line to the MVE Fusion freezer fill valve. Fill Valve Vent Valve 5.
MVE FUSION Quick Reference Guide Set up / Filling Procedure 1. Load racks and empty boxes into the MVE Fusion. NOTE: VERY IMPORTANT TO ADD RACKS AND BOXES BEFORE FILLING. 6 – 21205647 B...
Page 7
2. Connect the temperature probe to backside of the liquefier. Shut off isolation valves. They are located underneath the shroud on both sides of the liquefier 4. Connect A/C electrical power to MVE Fusion power receptacle at the rear. 7 – 21205647 B...
Page 8
MVE FUSION Quick Reference Guide At startup, the MVE Fusion Controller Main Screen will automatically display by default. Below shows the default LCD startup order. No programming required for the first fill. MVE Fusion Password: Fusion01 6. The Lid is installed during the fill process.
Page 9
LN2 will periodically spray out of the freezer vent valve. When a steady stream of LN2 exits the vent valve, the cryogen vessel is full (the vent valve may spray and sputter for several minutes prior to discharging a steady stream of liquid). The MVE Fusion first fill will take approximately 35 to 45 minutes.
MVE FUSION Quick Reference Guide Calibration of Temperature Probe Temperature sensor probe (A) used with the MVE Fusion has been calibrated at the factory using the “Low Temperature Range” method. This calibration method provides a level of ◦ ◦ accuracy of +/- 1.8...
VFD OVER CURRENT VFD over current VFD OVER TEMPERATURE VFD over temperature If any alarms occur, contact your authorized MVE Distributor or Customer / Technical Service Customer / Technical Service: Phone: (800) 482-2473 Fax: (888) 932-2473 11 – 21205647 B...
Page 13
MVE FUSION Quick Reference Guide 21205647 Rev B Chart Inc. reserves the right to discontinue its products, or change the prices, materials, equipment, quality, descriptions, specifications and/or processes to its products at any time without prior notice and with no further obligation or consequence. All rights not expressly stated herein are reserved by us, as applicable.