Evolion
3.9 kWh
®
Installation and operation instruction sheet
1. Introduction
The Evolion
®
is a Li-ion battery system that includes large format Li-ion cells and
necessary electronics for automatic interruptions or regulated operations when un-safe
limit is exceeded and detected.
This sheet is a quick start guide. It describes how to install and operate the Evolion
in a legacy battery mode, i.e., with no RS485/Modbus communication connected.
Within this sheet, the necessary tasks are noted with Ev#'s and they are in order that
they should be conducted. Use the Evolion
for records. Make sure to read the Evolion
Manual (UM), the Evolion
3.9 kWh Technical Manual (TM) and the Evolion
®
Software User Manual (CM). Check with your local Saft Representative for more details.
2. Safety
Misusing the Evolion
may cause an event
®
like cell venting, overheating or igniting.
Read these instructions fully before
■ ■
installing and operating the Evolion
Do not short-circuit the power
■ ■
terminals.
Do not reverse connect the power
■ ■
cables to the charger.
Do not disassemble the unit.
■ ■
Do not drop the unit.
■ ■
Do not immerse the unit.
■ ■
Do not expose the unit to fire or
■ ■
temperature higher than 80°C
(176°F).
Connect only to telecom power
■ ■
systems/rectifiers with a maximum
rated output of 60 V.
Refer to the Battery Information
■ ■
Sheet or BIS (included) for
emergency response procedures
and personal protective equipment
in case of an abnormal event.
If smoke is emitted from the
■ ■
module, stay clear of the smoke and
evacuate the area immediately.
For normal handling and operation
■ ■
according to this installation and
operation sheet, no personal
protective equipment is required.
3. Tools
These tools are needed and are not
provided.
Tool
Use
Voltage and fuse continuity
Front cover removal/
replacement
Grounding point screw
Power and fuse terminals
External case notations
BMST reset button
®
3.9 kWh historical data sheet (included)
®
3.9 kWh Installation and Operation User
4. Unpacking and Inspection
The Evolion
is packaged in accordance
®
with UN3480 Class 9 Group 2. See
Figure 1 for lifting instructions.
.
®
Check that all items are
Ev1
received.
If items were not received or if anything
was damaged do not install the module
and contact your local Saft representative.
Ev2 Study Evolion
features.
®
Check the state after
Ev3
receiving and before
storage or installation.
Always keep the Evolion
kit in its original packaging, together.
5. Storage
Store the battery in its original packaging.
• 15°C to 35°C (59°F to 95°F).
• No direct sunlight, rain or flooding
• Up to 1 year without refreshing charge
After 6 months, check the
Ev4
state once per month in
storage.
IMPORTANT: Never leave the Evolion
ON when it is not in use. The internal
electronics will self-discharge the cells
to a low voltage alarm level which may
render the module un-usable.
6. Transportation
Follow the necessary transportation
rules for Li-ion batteries by consulting
with your company's standard practice
and your local transportation regulations.
• Use the original packaging or equivalent.
• Secure the Evolion
in place
®
• The Evolion
must be OFF.
®
7. Installation
Before installing, make sure the right
number of Evolion
you will connect to
®
one bus is properly sized. Consult with
your local Saft Representative or consult
with the Evolion
TM.
®
Size the proper number
Ev5
of Evolion
®
to connect to
one bus.
Before installing, double check the state
of each Evolion
.
®
Ev6
®
If modules have more than 2 V difference
equalizing the Evolion
necessary, refer to the Evolion
Toolbox
®
Ev7
The Evolion
operated in Network Telecommunication
Facilities including un-manned OSP. The
Table 1
Evolion
battery compartments with the following
characteristics.
• IP54 (NEMA3) or higher
• -40°C to 75°C (-40°F to 167°F)
Figure 3
• 95% RH max. (non-condensing)
Figure 1
• Up to 3000 meters (9843 feet)
Figure 4
• No blocking the heat sink and vent ports
Table 2
• Right side up or sideways
module and its
®
Ev8
Ev9 Power ON
8. Operation/Maintenance
The Evolion
power anytime the AC power supply is
OFF. Continue trouble free operation in
Table 2
accordance with these instructions.
Figure 4
The Evolion
but periodically checking it during other
®
site routines is recommended.
• LED state (Table 3 and 9.
Troubleshooting)
• SOC and SOH (Table 2)
• Heat sink area un-obstructed
• Clean any excessive dirt build-up using a
nonmetallic brush or a dry or damp cloth.
• Do not use any cleaning solvents or soaps.
• Do not immerse, bathe or hose off the
Evolion
9. Troubleshooting
When the Evolion
the LED's. See Table 3 for operation
LED state.
LED
state
D
E
Evolion
®
TM
G
May 2016
Check for a maximum of
Figure 1
2 V difference allowed
Figure 4
between modules that will
operate on the same bus.
modules is
®
UM.
®
For modules that will
Figure 6
operate on the same bus,
(manual)
set each with a unique
or
Node ID, manually between
Evolion
CM
1 to 4 or using the Evolion
®
Toolbox Software.
(software)
can be installed and
®
can be placed on shelves or in
®
Connect the Evolion
Figure 8
®
modules.
Figure 9
Figure 10
provides un-interrupted standby
®
requires no maintenance,
®
.
®
is in service, observe
®
Refer to
Evolion
TM, Appendix E
®
Evolion
TM, Appendix E; Figure 11
®
IMPORTANT: The Evolion
®
must
be re-charged within 2 weeks after
Alarm #36 was activated or the
module may be rendered useless.
Figure 11
®
Need help?
Do you have a question about the Evolion and is the answer not in the manual?
Questions and answers