GENERAL INFORMATION

General installation methods are designed to simplify the installation process by allowing the best method to be utilized
for each jobsite depending on conditions and use. In the residential and commercial application these options are loose
laid, releasable bond, and permanent bond. See page 4 for recommended use chart.
These instructions cover all installation methods of Mannington Residential and Commercial Insight
All recommendations are based on the most recent available information. The information on these sheets provides
general guidelines. For complete details consult Mannington's General Installation Guide or visit our website
at manningtoncommercial.com. These instructions and recommendations must be followed for a satisfactory installation.
The installation of Mannington Insight
quality resilient fiberglass backed sheet floors. Good preparation is essential for a trouble-free installation. Do not install
Mannington resilient flooring until jobsite testing and subfloor preparations are finished and the work of all other trades is
complete. Site conditions must comply with the relevant building codes and local, state and national regulations.
Documentation of Moisture and pH test results is required when processing claims.
• Mannington Insight
Plus GB is recommended for use over properly prepared concrete, suspended wood, metal and
®
other suitable substrates. Never install Mannington Insight
"Bleed Through" may occur.
• Mannington Insight
Plus GB can be used with radiant heating systems (maximum subfloor surface temperature of 85° F).
®
• Mannington Insight
Plus GB is not suitable for external installation or unheated locations.
®
• Mannington resilient flooring, adhesive, jobsite and subfloor must be acclimated to a stable condition before installation.
• Following installation, Mannington Insight
rolling traffic for 48 hours when the pressure sensitive and permanent bond methods are used.
• Mannington Insight
Plus GB flooring should remain at a temperature between 55°-85° F (13°-27° C) during its service life.
®
• Always follow other manufacturers' written recommendations when using their proprietary materials for subfloor
preparation.
MATERIAL RECEIVING, HANDLING & STORAGE
1. Always store Insight
Plus GB tightly rolled, face out on a sturdy cardboard core designed for that purpose. Store the
®
roll horizontally and support it across the entire width. Notice the Insight
important information such as product name and run date. Before starting the job, always check the flooring materials
to ensure they are the correct pattern, style, and color. Also make the sure the size and amount of the products are
sufficient to complete the installation. Inspect the material closely before installation for any visible defects.
Mannington Flooring products are manufactured to high quality standards and are carefully inspected before leaving
our facility. Occasionally, however, defects are not detected. If you notice a visible defect in the flooring product,
stop the installation and contact your local Mannington Distributor for assistance.
2. Report discrepancies immediately to Mannington Customer Service at 1-800-356-6787 (residential) 1-800-241-2262 EXT 2
(commercial) Claims for installation of products installed with visual defects or incorrect style will not be honored.
3. Store all materials in a weather-tight enclosure between 55°-90° F (13°-32° C).
4. Acclimate flooring, adhesive and jobsite to a stable condition between 65°-85° F (18°-29° C) and 50% +/- 10% RH for 48
hours before, during and after installation. Acclimate all materials onsite. Temporary heating and cooling should be used
if permanent HVAC is not operational.

JOBSITE TESTING

1. Before jobsite testing, the house/building envelope must be sealed (walls, roofing, windows, doorways etc., installed).
2. Anticipated environmental conditions must be maintained at 75°F +/- 10°F (24°C +/- 6°C) and 50% +/- 10% RH a
minimum of 48 hours before and during testing (ASTM F 710).
3. Test sites must be properly prepared and protected for the duration of testing to achieve valid results.
4. Surface Flatness for all Subfloors: The surface shall be flat to 1/8" in 10 ft (3 mm in 3 m). To check flatness, place a
10 ft straight edge on the surface and measure the gap or use another suitable method.
5. Concrete Subfloors:
a. Concrete subfloors must be finished and cured without additives, curing compounds, hardeners or surface
treatments that may prevent proper bonding of the flooring materials (ACI 302.1 and ASTM F710).
Choices that Work.
Questions about warranties? call 800 241 2262 or visit www.manningtoncommercial.com
Plus GB is straight forward and similar to the installation procedures that apply to all
®
Plus GB over residual asphalt type (Cutback) adhesive as
®
Plus GB should be protected from traffic for 24 hours, point loads and
®
Insight
Installation Guidelines
Plus GB.
®
Plus GB printed pattern backing provides
®
Plus GB
®
July, 2015

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Insight Plus GB and is the answer not in the manual?

Questions and answers

Summary of Contents for Mannington Insight Plus GB

  • Page 1 Good preparation is essential for a trouble-free installation. Do not install Mannington resilient flooring until jobsite testing and subfloor preparations are finished and the work of all other trades is complete. Site conditions must comply with the relevant building codes and local, state and national regulations.
  • Page 2 If the water droplet does not dissipate within 60 to 90 seconds the subfloor is considered non-porous. If the substrate is too porous apply Mannington Premium Universal Primer to render the surface suitable for adhesive and floor covering.
  • Page 3 8. Particleboard, chipboard, construction grade plywood, any hardboard and flake-board are not recommended as underlayment for fully adhered installations. All have inadequate uniformity, poor dimensional stability, and variable surface porosity. Mannington Resilient Floors will not accept responsibility for adhered installation over these subfloors. Insight Plus GB loose laid method can be installed over all wood and wood composition panels provided that they are ®...
  • Page 4 (Unconditioned wood panel substrates are not dimensionally stable and are subject to too much movement.) Check the porosity of the subfloor and, if necessary, use Mannington’s Premium Universal Primer to prevent over absorption of adhesive. To achieve a Releasable Bond, the MT- 711 is applied over the substrate with a 3/8 nap paint roller and allowed to dry to tack before positioning the Insight Plus GB into the adhesive.
  • Page 5 Plus GB only when using the fully ® adhered method. Note: Mannington Insight Plus GB foam backing has important printed information which identifies product name and ® production dates. The distinctive printed pattern is also helpful during installation while cutting in the product. The printed arrows become useful when identifying material direction for seaming.
  • Page 6 Cut the second and all succeeding sheets to the next multiple of the pattern repeat over the net room dimension, providing the starting wall is the same. SEAM CUTTING Seaming is one of the most important aspects of resilient sheet installation. Always double-cut seams in Mannington Insight ® Plus GB with a new, sharp utility knife blade.
  • Page 7 Plus GB can be Flashed Coved when only using the permanent full spread application. Apply Mannington’s MT ® 711 or V-88 with a brush or paint roller. Seal all coved corners using Mannington’s MLG 33 seam sealer. FINISHING & MAINTENANCE Molding &...
  • Page 8 Insight Plus GB ® Installation Guidelines REPAIRS Small Cuts Small cuts will eventually gap open. To repair, clean any dirt from the cut and apply MLG-33 seam sealer. Replacing Damaged Areas – Plugs If you must replace a damaged area, follow these steps: •...