Operation – and Assembly Instruction DRIESCHER WEGBERG -insulated Switchgear Type MINEX-E 12-36kV State 05-2017...
Page 2
DRIESCHER WEGBERG Alle Rechte vorbehalten / All rights reserved DRIESCHER WEGBERG 2017 ® MINEX...
Page 3
Place the switchgear on plain and horizontal concrete foundations or intermediate frames with sufficient capacity to avoid the deformation of the switchgear cubicles. Preliminary measures: DRIESCHER WEGBERG Vierkantrohr Parallelzwinge Check the completeness of the necessary components and tools.
Page 4
3) Screw the spacing bushes (5) tight as shown. DRIESCHER WEGBERG DRIESCHER WEGBERG 4) Replace two non-sealed inner hexagon screws per phase by the cylinder head screws (4), if these are not factory available.
Page 5
Coincident the screws in the base box have to be towards the holes. DRIESCHER WEGBERG DRIESCHER WEGBERG 7) Lead the switching cubicles parallel together. Take care not to tilt the cubicles.
Page 6
11) Place the screws M8x30 into the holes provided, and tighten these hand-tight (see drawing HB71553-001 Pos. 5). DRIESCHER WEGBERG 12) Loosen the clamps and put them aside. 13) Place the delivered distance sheet steels (8) between the sides whereby the grooves grab over the screws (see drawing HB71553-001 Pos.
Page 7
Do not loosen sealed screws. For coupling of the switching cubicles please proceed as described under point 1 – 14! If you have questions please contact the service department of company Fritz Driescher KG in Wegberg, phone 0049 (0)2434/81-1 ® MINEX...