Celuplast Guardian Roof Installation Manual

Advertisement

Quick Links

Guardian Roof Installation Guide
The following guide has been created to assist in the
fabrication and installation of the Celuplast Guardian
Roof. Please note that each roof is individual and will be
fabricated to suit various shapes and sizes.
Each roof supplied will be accompanied by a roof layout
plan and this guide. Your fabricator will be available at
all reasonable times to provide installation technical
support.
Roof Layout Plan
Please refer to the roof layout plan prior to commencing
installation. It is very important that the roof fits the
windows layouts and that all the windows are
reinforced. All components are numbered to match the
roof layout plan for ease of installation.
Sealing
At important junctions on the roof it is important to use
a suitable sealant to secure a water tight joint.

Advertisement

loading

Summary of Contents for Celuplast Guardian Roof

  • Page 1 Guardian Roof Installation Guide The following guide has been created to assist in the fabrication and installation of the Celuplast Guardian Roof. Please note that each roof is individual and will be fabricated to suit various shapes and sizes. Each roof supplied will be accompanied by a roof layout plan and this guide.
  • Page 2 Snips and Staple gun Screwdriver Important Celuplast have taken great care to ensure that the information in this installation guide is accurate and is supplied in good faith. However Celuplast issues this guide without warranty or guarantee of any kind and accepts no responsibility as to how the information is interpreted.
  • Page 3 All window frames must be reinforced in order to take the weight of the Guardian Roof. It is the sole responsibility of the installer to establish that the window frames are reinforced.
  • Page 4 Box Gutter Components...
  • Page 5 1. Fix window frame to ring beam 2. Fix ring beams together using self tapping screws at a using ring beam cleats maximum if 600mm centres...
  • Page 6 3 Connect ring beams together 4 Connect rafters to ring beam using cleats and self tapping screws using cleats and bolts provided 5 Assemble carcase as per layout plan Typical Spider assembly using pins 6.Gable rafters to be secured to and locking nuts provided the house wall using suitable fixings depending on wall...
  • Page 7 The overhang is 200mm. Fakro Window to be fitted to the V Fakro Tile Flashing installed with Notch Guardian Roof Tile Tiling always to start at the bottom left of the roof. Always start with a full tile with a half tile above.
  • Page 8 Fix timber with expanding foam tape to roof with wood screws. Then fix ridge cappings followed by cappings. All cappings to be screwed from the side and hidden using the Guardian Tile repair kit. Gutter brackets twist lock into the ring beam and Gutter locks on. to brackets. Box Gutter adapter fitted into the box gutter and sealed using suitable wet sealant.