SECTION 2-Front Frame Conversion

2.1-General lnformation
The Front Frame Conversion consists of the following:
1. Relocating the W Relay on quick-close, electrically
operated, Type AK-50/75/1 00 breakers equipped with EC
trip devices.
2. Remounting the X Relay on the same breakers
described above.
3. Installing the Flux Shifter device.
4. Installing the Programmer Mounting bracket.
5. Installing the Programmer Wire harness.

2.2-Breaker Disassembly

BEFORE STARTING ANY WORK, DIS­
WARNING:
CONNECT THE BREAKER FROM ALL POWER
SOURCES (PRIMARY AND SECONDARY) AND
PLACE IN A CLEAN WORK AREA.
Verify the breaker is OPEN. Referring to the appropriate
Maintenance Manual, See Table 1-6, separate the breaker's
front and back frames.
FRONT VIEWS OF BREAKER
BEFORE
Fig. 2-1. Relocating W -relay and remounting X-relay

2.3-Remounting W and X Relays

Type AK-2/2A Breakers (EC trip devices) electrically­
operated with quick-close may require the relocation of
their anti-pump, W-Relay to insure proper space for the
MicroVersaTriprM programmer unit. On these breakers,
the W Relay normally mounts on the left side of the center
channel, sharing a common mounting bracket with the
X Relay as shown in Fig. 2-1.
Remove the W-relay and using the new mounting bracket
provided, See Fig. 2-2, relocate the mounting bracket to the
upper-left side of the front frame, as shown in Fig. 2-1.
Remove"the X Relay and its mounting bracket. Using the new
bracket provided, see Fig. 2-2, remount the X Relay in its
existing location, as shown in Fig. 2-1.
Type AKA and AKS Breakers do not require remounting of
their W and X Relays.
--... .. .
-
�)