Startup and Test
Before turning on the unit, the following checks are to be performed by Qualified Personnel.
•
L1, L2, and L3 are connected to the 3-phase input power.
•
T1, T2, and T3 are connected to the motor.
•
The 3-phase input voltage is within the ASD setup tolerances.
•
There are no shorts and all grounds are secured.
•
With the previous checks confirmed, ensure that the direction of the motor rotation in the Bypass
mode and in the ASD-driven mode is consistent.
•
Ensure that all personnel are clear of the motor and the motor-driven equipment.