8. Head Lever adjustment
Establish the working position of the Solenoid; then adjust the gap between the head of the Hood
Assembly and the platen.
Attach the two mounting screws
<.
The plunger should move smoothly.
9. Hook the Tension Spring to the Head Lever.
Adjust the Thermal Head pressure with the adjustment Nut
@.
(Refer to Figure 49. Thermal Head
Assembly Replacement.)
10. Adjust the Thermal Head Assembly pressure as follows:
Using a Spring Gauge, push on the bottom of the Thermal Head Assembly at point B.
Adjust the pressure level with Nut
(6).
A pressure level of 150
-
185g should be required to move
the head. (use tension gaze)
NOTE: Item 10 adjustment is related to printing Density. Therefore, this adjustment should be done
with regard to Printing Density Adjustment on the P.C.B. If the Pressure is high. printing should