II. Boiler Assembly
A.
Remove Crate
1. Remove all fasteners at crate skid.
2. Lift outside container and remove with all other
inside protective spacers and bracing.
B.
Remove boiler from skid. See Figure 2. Exercise care
to avoid dropping boiler.
1. Place boiler in approximate location. Refer to
Section I: Pre-Installation. Remove base hold down
bolts.
2. Using pry bar under rear corner of Base End Panel,
raise boiler and install 1½" wood blocks under rear
corners. Install ¾" pipe roller between Base and
skid.
3. Remove 1½" wood blocks. Place 3" pipe roller on
floor behind skid.
4. Roll boiler off skid. Move skid out of way.
5. Roll boiler until 3" roller is located as shown. Use
pry bar to install wood blocks under front corners of
base. Remove 3" roller.
10
Figure 3: Tapping Locations
Table 3: Purpose of Tappings
Tapping
Size
A
2"
B
2"
C
3/4"
D
3/4"
E
3/4"
F
3/4"
G
3/4"
Figure 2: Skid Removal
Purpose
Supply
Return
Relief Valve
Limit
Auxiliary Limit
Washout
Drain