2

Prepare boiler

Remove boiler from wood pallet

1. After removing the outer shipping carton from the boiler,
remove the parts box.
2. Remove the front door to access the lag bolts in front of
the unit (FIG. 2-1).
3. To remove the boiler from the pallet (after removing the
front door):
a.
Remove the two lag bolts from the wood pallet
inside the boiler (FIG. 2-1).
b. Detach the boiler from the lag bolts in the rear of the
unit, see FIG. 2-1.
Do not drop the boiler or bump the jacket
NOTICE
on the floor or pallet. Damage to the
boiler can result.
Figure 2-1 Boiler Mounted on Shipping Pallet

Gas conversions

For a boiler already installed, you must
WARNING
turn off gas supply, turn off power and
allow boiler to cool before proceeding.
You must also completely test the boiler
after conversion to verify performance
as described under Start-up, Section 10
of this manual. Failure to comply could
result in severe personal injury, death, or
substantial property damage.
You must install a propane orifice to
operate the Knight boiler on propane gas.
Verify when installing that the orifice size
marking matches boiler size (Table 2A).
1. Remove the top and front access covers from the unit (no
tools required for removal).
2. Remove the three screws securing the gas valve to the
venturi (FIG. 2-2).
3. Locate the propane orifice disk from the conversion kit
bag. Verify that the stamping on the orifice disk matches
the boiler size (see Table 2A).
Place the orifice into the black rubber grommet in the
side of the gas valve and secure in the valve (FIG. 2-2).
4. Reposition the gas valve against the venturi and replace
the screws (FIG. 2-2) securing the valve to the venturi.
5. After installation is complete, attach the propane conversion
6. Replace the top and front access covers.
Table 2A LP Conversion Table
Figure 2-2 Installing Propane Orifice
. 2

Leveling the boiler

1.
Figure 2-3 Leveling Legs on the Boiler
Installation & Operation Manual
label (in the conversion kit bag) next to the boiler rating
plate. Attach the LP caution label (in the conversion kit
bag) to the left side of the unit in the lower left corner.
LP Conversion Table
Model
81
106
151
211
286
After converting to LP, check combustion
WARNING
per the Start-up procedure in Section 10
of this manual. Failure to check and verify
combustion could result in severe personal
injury, death, or substantial property damage.
Set the boiler in place and check level.
a) Adjust legs if necessary to level boiler, see FIG. 2-3
below.
LP Orifice Stamping
80
105
150
210 / W150
285
13