Installation For Vertical Termination - Desa (V)T32N-A series Owner's Operation And Installation Manual

Direct-vent
Table of Contents

Advertisement

INSTALLATION FOR vERTICAL
TERMINATION
Note: Vertical restrictor must be installed in
all vertical installations.
1. Determine route your vertical venting
will take. If ceiling joists, roof rafters or
other framing will obstruct venting system,
consider an offset (see Figure 19) to avoid
cutting load bearing members. Note: Pay
special attention to these installation
instructions for required clearances (air
space) to combustibles when passing
through ceilings, walls, roofs, enclosures,
attic rafters, etc. Do not pack air spaces
with insulation. Also note maximum
vertical rise of venting system and any
maximum horizontal offset limitations.
2. Set fireplace in desired location. Drop a
plumb line down from ceiling to position
of fireplace exit flue. Mark center point
where vent will penetrate ceiling. Drill a
small locating hole at this point.
Drop a plumb line from inside of roof to
locating hole in ceiling. Mark center point
where vent will penetrate roof. Drill a small
locating hole at this point.
Wall Strap
Figure 19 - Offset with Wall Strap and 45°
Elbows
14
VENTING INSTallaTION
Continued
Roof
Flashing
45° Elbow
Ceiling
Firestop
www.desatech.com
Flat Ceiling Installation
1. Cut a 11
/
" square hole in ceiling using locat-
1
2
ing hole as a center point. Opening should be
framed to 11
/
" x 11
1
2
as shown in Figure 9 on page 9 using framing
lumber the same size as ceiling joists. If area
above the ceiling is an insulated ceiling or an
attic, nail firestop from top side. This prevents
loose insulation from falling into required
clearance space. If area above ceiling is a
living space, install firestop below framed
hole. Firestop should be installed with no less
than 3 nails per side (see Figure 20).
2. Assemble desired lengths of pipe and
elbows necessary to reach from fireplace
flue up through firestop. Be sure all pipe
and elbow connections are fully twist-
locked (see Figure 8, page 9).
3. Cut a hole in roof using locating hole as
a center point. (Cover any exposed open
vent pipes before cutting hole in roof.) The
11
/
" x 11
/
" hole must be measured
1
1
2
2
on the horizontal; actual length may be
larger depending on pitch of roof. There
must be a 1" clearance from vent pipe to
combustible materials. Frame opening as
shown in Figure 9, page 9.
4. Connect a section of pipe and extend up
through hole.
Note: If an offset is needed to avoid
obstructions, you must support vent pipe
every 3 feet. Use wall straps for this pur-
pose (see Figure 19). Whenever possible,
use 45° elbows instead of 90° elbows. The
45° elbow offers less restriction to the flow
of flue gases and intake air.
5. Place flashing over pipe section(s) ex-
tending through roof. Secure base of
flashing to roof and framing with roofing
nails. Be sure roofing material overlaps
top edge of flashing as shown in Figure
19. There must be a 1" clearance from
vent pipe to combustible materials.
If area above is an
attic or insulated
area, install firestop
above framed hole.
Figure 20 - Installing Firestop
/
" inside dimensions,
1
2
If area above is a
living space, install
firestop below framed
hole.
116646-01H

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents