36 COMMIssIONINg AND TEsTINg

A. Electrical Installation
1. Checks to ensure electrical safety should be carried out by a
competent person.
2. ALWAYS carry out the preliminary electrical system checks,
i.e. earth continuity, polarity, resistance to earth and short
circuit, using a suitable test meter.
Warning.
Whilst effecting the required gas tightness test and purging air from the gas installation,
open all windows and doors, extinguish naked lights and Do noT sMoke.
gENERAL
Please note: The combustion for this appliance has
been checked, adjusted and preset at the factory for
operation on the gas type defined on the appliance
data plate. No measurement of the combustion is
necessary. DO NOT adjust the air/gas ratio valve.
Having checked:
-
That the boiler has been installed in accordance
with these instructions.
-
The integrity of the flue system and the flue seals,
as described in the Flue Installation section.
Proceed to put the boiler into operation as follows:
ChECK ThE OpERATIONAL (WORKINg) gAs
CH Flow
INLET pREssURE
DHW Outlet
Set up the boiler to operate at maximum rate by
opening hot tap to maximum
flow.
With the boiler operating in
the maximum rate condition
check that the operational
(working) gas pressure at
the inlet gas pressure test
Black
point complies with the
Handle
requirements - refer to "Gas
Supply" on page 8.
Ensure that this inlet pressure
can be obtained with all other
gas appliances in the property
working.
IT Is A CONDITION OF ThE MANUFACTURERs WARRANTy ThAT ThE
BENChMARK COMMIssIONINg ChECKLIsT Is FULLy COMpLETED
+
Ideal Logic
Combi -
INsTALLATION
Gas Supply
Yellow
Handle
Gas Pressure
Test Point
AND LEFT WITh ThE AppLIANCE
Installation and Servicing
B. gas Installation
1. The whole of the gas installation, including the meter,
should be inspected and tested for tightness and purged in
accordance with the recommendations of BS. 6891.
In IE refer to IS.813:2002.
2. Purge air from the gas installation by the approved methods
only.
DHW Inlet
CH Return
Blue
Handle
3G9927
ATTENTION !
Safety
Drain
Valve
Black
Handle
33