Engine Assembly (Station Wagon); Cylinder Head Stud Nut Tightening Sequence.500 D. F And L Sedan And Station Wagon; Power Plant Rear Suspension - Fiat 500L Workshop Manual

Fiat 500 1957-73
Hide thumbs Also See for 500L:
Table of Contents

Advertisement

sections of the air conveyor securing with seven
screws, seven toothed washers and five nuts.
22 Slide the fuel pump control rod into its seating,
assemble the insulator between oil wetted graphite
gaskets and fit the pump to the crankcase using nuts
and toothed washers.
23 Fit the air conveyor cover complete with the accelera-
tor control relay lever and rod. Secure using eight
mounting screws, eight toothed washers, eight plain
washers and eight nuts. Fit the fuel line retaining clip
which is secured by one of the air conveyor upper
screws. Install the generator and fan drive pulley
having first placed four adjusting rings between the
pulley halves and the thrust ring on the outside.
Secure the pulley to generator shaft using three
screws and three toothed washers. Fit the generator
fan drive belt.
24 Refit the carburetter having first positioned the
bakelite heat shield between the two oil moistened
graphite gaskets. Secure the carburetter using two
copper washers and two self-locking nuts. Fit the
exhaust silencer and secure to the exhaust manifolds
with nuts and spring washers. Place the two graphite
gaskets between the manifold joints. Fit both exhaust
silencer upper mounting brackets and secure them
on the top side to the brackets already in place with
nuts and toothed washers on the bottom side with
screws and toothed washers.
25 Carefully position the distributor at a 10 deg advance
setting and secure with a nut, plain washer and
spring washer. Fit the fuel pump to carburetter line
complete with mounting bracket rubber lining and
secure the line with two clamps. If difficulty is
experienced in positioning the fuel line into the pump
or carburetter funnels it is suggested that the line
ends should be heated in hot water and thoroughly
dried before installing.
26 Install the air cleaner elbow and rubber hose assembly
on the top of the carburetter using a graphite gasket
in between and secure with nuts, plain washers and
spring washers. Carefully position the air cleaner, line
and hose assembly and connect it to the elbow.
Secure the cleaner to air conveyor cover using screws
and toothed washers.
27 Fit the spark plug cables complete with the rubber
grommet for cable mounting bracket on engine
cowling and connect the cables to the distributor
and spark plugs. Fit the oil pressure gauge sender
unit together with its sealing washer.
28 Install the cylinder head cover and oil breather pipe
assembly with a cork gasket inserted between.
Secure with self-locking nuts and fibre washers.
Connect the accelerator control relay lever rod to the
carburetter and secure with the clip.
29 Fill the oil pan with the correct grade and quantity of
oil, insert the dipstick and the engine is ready for
refitting.

1:18 Engine assembly (station wagon)

Reassembly of this engine is straightforward as it is
the reverse procedure to dismantling. It is recommended
that Sections 1 :5 and 1 :17 are studied as the assembly
technique is similar for both the horizontal and vertical
F500
FIG 1:46
Cylinder head stud nut tightening sequence.
500 D. F and L Sedan and Station Wagon
FIG 1 :47

Power plant rear suspension

Key to Fig 1 :47
1
rubber pad to bracket
4 Nut, arm to bracket
7 Arm pin-to-support nut
9 Pin arm to support
cylinder engines. The following points should however
be noted:
1 Refer to FIG 1 :45 for the correct positioning of the
connecting rod-piston assembly on the 120.000
engine.
2 The sequence of tightening the cylinder head nuts is
different, the new order being given in FIG 1 :46.
Suspension arm
2 Screw,
3 Bracket-to-engine nut
5 Arm bracket
6 Spring
8 Screws, pin to support
31