machine components during shipping. A full operating oil charge is placed in the oil sump
before shipment.

Identify Machine

The machine model number, serial number, and heat exchanger sizes are stamped on the
machine identification nameplate
shipping papers and job data.
Click here for Figure 1 — Model Number Identification
Click here for Figure 2 — Typical 19FA Installation (1400-2200 Tons
[4922-7735 kW])

Provide Machine Protection

Protect machine and starter from construction dirt and moisture. Keep protective shipping
covers in place until machine is ready for installation.
If machine is exposed to freezing temperatures after water circuits have been installed, open
waterbox drains and remove all water from cooler and condenser. Leave drains open until
system is filled.