INSTALLATION

Jobsite Survey
Complete the following checks before installation.
1. Consult local building codes and the NEC (National
Electrical Code) ANSI/NFPA 70 for special installa-
tion requirements.
2. Determine unit location (from project plans) or select
unit location.
3. Check for possible overhead obstructions which may
interfere with unit lifting or rigging.
Step 1 — Plan for Unit Location
Select a location for the unit and its support system (curb
or other) that provides for the minimum clearances
required for safety. This includes the clearance to
combustible surfaces, unit performance and service access
below, around and above unit as specified in unit
drawings. See Fig. 3.
NOTE: Consider also the effect of adjacent units.
Unit may be installed directly on wood flooring or on Class
A, B, or C roof- - covering material when roof curb is used.
Do not install unit in an indoor location. Do not locate air
inlets near exhaust vents or other sources of contaminated
air.
Fig. 2 - - Unit Dimensional Drawing – Size 24 Unit (cont.)
36" (914)
42" (1067)
Fig. 3 - - Service Clearance Dimensional Drawing
Although unit is weatherproof, avoid locations that permit
water from higher level runoff and overhangs to fall onto
the unit.
Select a unit mounting system that provides adequate
height to allow installation of condensate trap per
requirements. Refer to Step 9 — Install External
Condensate Trap and Line – for required trap dimensions.
Roof mount —
Check
building
codes
requirements. Unit operating weight is shown in Table 1.
6
C10138
42" (1067)
18" (457)
C09121
for
weight
distribution