3. INSTALLATION - Page 4
Keep
Fig. 2
Bottom Cover
Bag Of
Accesories
Fig. 3
Cover
Terminals
With 2 Studs
Fig. 4
Flue
Terminal
(4 - Stud Terminal Shown)
Outer Case
Cover
Terminals
With 4 Studs
A.
LOCATION
1.
If the appliance is to be fixed to a suitable existing
terminal first isolate and remove the old appliance.
Leave the flue terminal in place. Retain the fixing nuts
and washers. Make good any damage to the brickwork
or plaster around the terminal. Cut off the existing
pipework at a convenient point below the appliance.
2.
If installing a new flue terminal, guidance is given on
the template sheet supplied with the terminal pack.
NOTE: Where the appliance is to be installed into a
SEDUCT the minimum duct required is 228mm (9in) deep,
349mm (15 ½ in) wide.
3.
Where the building regulations require it, a flue terminal
guard should be fitted symmetrically around the outer
part of the flue terminal.
4.
Unpack the water heater. Find the bags of accessories
before discarding the packaging.
5.
Slide off the bottom cover then remove the three
screws securing the outer case and carefully lift it off.
6.
Use the self adhesive discs supplied to cover the
unwanted fixing holes in the back of the new appliance
as shown.