Installation
This boiler is certified for closet installations. To ensure
adequate access to the boiler during installation and
maintenance, the boiler should have a minimum space
in front of the boiler of at least 33" with the access door
open. When the access door is closed, a minimum
clearance of 2 inches in front and on the sides of the
boiler from combustibles is required (Fig.3). Maintain a
minimum clearance from combustibles of 2 inches for
the exhaust vent pipe. A 20" top clearance is
recommended for cleaning access and is strictly
required when the boiler is placed in a fully enclosed
closet. A 2" rear clearance is required for horizontal vent
pipe installations. The gas boiler is certified for
installation on combustible flooring. The boiler must not
be installed on carpeting.
Provide 2" clearance between vent pipe and
combustible construction.
No clearance is required between wall terminal body
and combustible construction
5.1

Transporting the Boiler

z Transport the boiler to the installation site in the
shipping carton and on the pallet.
z Remove strapping and lift off carton.
z Remove the two bolts that secure boiler to the
wooden pallet.
z Lift the boiler from one side and slide to the side of
the pallet. Push a pipe under the boiler as shown in
Fig. 4 and roll boiler on several pipes to its final
location.
z Move the boiler to its final installation position.
NOTICE !
Always protect sheet metal parts, gas
pipe, burner and control panel during
handling.
z Never lift the boiler on these parts.
We reserve the right to make any changes due to technical modifications!
Installation, Operation and Maintenance Manual Sealed Combustion Gas Boiler Logano GA244 • Issue 02/2004
8
1
2"
Fig. 3
Minimum clearances from combustible construction
Item. 1: Access door closed
Item. 2: Access door open
Item. 3: Exhaust vent pipe
Fig. 4
Moving the boiler