3.01 Checks to be carried out before starting up for the fi rst time
When firing the boiler up for the first time, it is good practice to check:
that the isolation valves between the boiler and central heating systems are open;
that the central heating system is well filled and vented;
that there are no gas or water leaks from the central heating system or boiler;
that the electric connections are correct and the earth wire of the boiler is connected to an efficient earthing
installation;
that there are no inflammable liquids or materials near the boiler;
that the central heating gas pressure and flow rate are as required.
3.02 Starting up the boiler
• Open the gas cock of the boiler.
• Vent air present in the pipe upstream of the gas valve.
• Turn on the switch (if present) or plug upstream of the boiler.
• Rotate the C.H. temperature adjustment knob above Min position.
• Set the room thermostat (if fitted) to maximum.
• At this point, the burner ignites and the boiler starts to function automatically, controlled by its control
and safety devices.
Note - If after completing the start-up procedure correctly, the burner fails to ignite and the boiler shut down warning
lights up, wait about 15 seconds then press the reset switch. The reset electronic control unit will repeat the start-up cycle.
If after a second attempt the burners still fail to ignite, consult the paragraph "Troubleshooting".
Note - If there is a power failure while the boiler is in operation, the burners automatically go out and re-ignite
when the power returns.
WARNING
If the system is filled with very cold water, the boiler will automatically light due to the frost thermostat sensing the low
temperature. The boiler will not shut down, until the water temperature reaches 10°C.
3.03 Shutting down
To shut down the boiler for short periods
• Set the temperature adjustment knob to "Off" position.
To shut down the boiler for long periods
• Turn off gas supply.
• Turn off the electricity supply.
IMPORTANT
The boiler is protected by integral frost protection, but if the boiler is not to be used for a long period of
time, the system should be drained.
Note: The frost thermostat operates even if the temperature adjustment knob is in the OFF position and it is necessary
therefore, if the system is drained, for the external electrical and gas supplies to be isolated.
It is recommended that a label be affixed to the appliance to draw attention to the fact that the system
has been drained.
3.04 Checks and tests after fi rst start-up
Check there are no leaks in the gas and water circuits.
Check correct boiler start up by carrying out start up and shut down tests using the boiler stat.
Check the integrity of the air-flue pipes during boiler operation.
Check that the gas consumption indicated on the meter corresponds to that given in Technical Data (paragraph
1.03).
Check that water is circulating correct.
does not exceed 20°C.
2 0
Balance the radiators to ensure that the flow and return differential
Sigma

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sigma 60-100

Table of Contents