Operation - MULTIQUIP GA-9.7HE Operation And Parts Manual

Honda gx610 gasoline engine
Table of Contents

Advertisement

This section is intended to assist the operator with the initial
start-up of the portable generator. It is extremely important
that this section be read carefully before attempting to use
the generator in the field.
Before starting the engine
1. Be sure to disconnect all electrical loads from the
generator prior to starting the engine.
2. NeveR start the engine with the main circuit breaker
in the ON position. Always place circuit breaker (Figure 11)
in the OFF position before starting.
Figure 11. Main Circuit Breaker (OFF)
3. NeveR start the engine with the GFCI or AUX. circuit
breakers in the ON position. Always place these circuit
breakers (Figure 12) in the OFF position before starting
the engine.
Figure 12. GFCI/AUX. Circuit Breakers (OFF)
starting the engine
4. Place the choke knob (Figure 13) in the ClOsed
position if starting a cold engine.
Figure 13. Choke Knob
5. Place the choke knob (Figure 13) in the OpeN position
if starting a warm engine or the temperature is warm.
page 22 — ga9.7He 60 Hz geNeRaTOR• OpeRaTiON aNd paRTs maNual — Rev. #1 (04/29/10)
6. Place the generator's operation switch (Figure 14) in
the ON position.
Figure 14. Operation Switch (ON)
7. Press the generator's pushbutton start switch (Figure
15) and listen for the engine to start. If the battery is
not installed proceed to step 6.
Figure 15. Start Pushbutton Switch
8. Grasp the starter grip (Figure 16) and slowly pull it out.
The resistance becomes the hardest at a certain
position, corresponding to the compression point. Pull
the starter grip briskly and smoothly for starting.
Figure 16. Starter Grip
NOTICE
dO NOT pull the starter rope all the way to the end.
dO NOT release the starter rope after pulling. Allow it
to rewind as soon as possible..
9. If the engine has started, slowly return the choke lever
(Figure 13) to the OpeN position. If the engine has not
started repeat steps 1 through 8.
10. Before the generator is placed into operation, run the
engine for 3-5 minutes. Check for abnormal smells,
fuel leaks, and noises that would associate with lose
components.

OperatiOn

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents