Example Of An Installation Schedule; Site Inspection Checklist - HP 9000 rp3410 Manual

Generic site preparation guide - edition 6
Hide thumbs Also See for 9000 rp3410:
Table of Contents

Advertisement

Conversion Factors
Refrigeration
— 1 watt = 0.86 kcal/hour
— 1 watt = 3.412 Btu/hour
— 1 watt = 2.843 × 10-4 tons
— 1 ton = 200 Btu/minute
— 1 ton = 12,000 Btu/hour
— 1 ton = 3,517.2 watts
Metric Equivalents
— 1 centimeter = 0.3937 inch
— 1 meter = 3.28 foot
— 1 meter = 1.09 yards
— 1 in. = 2.54 centimeters
— 1 ft. = 0.305 meters
— 1 CFM = 1.7m
kVA conversions
Three phase
kVA = V × A × √3 / 1000
Single phase
kVA = V × A / 1000
Formulas
kVA = voltage × current (amps)
Watts = VA × PF
Btu = Watts × 3.41
ºC = (32 + 1.8a) ºF

Example of an Installation Schedule

The following schedule lists the sequence of events for a typical system installation:
Sixty days before installation
— Floor plan design is completed and mailed to HP (if required to be an HP task).
Thirty days before installation
— Primary power and air-conditioning installation are completed.
— Telephone and data cables are installed.
— Fire protection equipment is installed.
— Major facility changes are completed.
— Special delivery requirements are defined.
— Site inspection checklist is completed. See
customer information forms and site inspection checklists.
— Delivery survey is completed. See
a sample delivery survey.
32
General Site Preparation Guidelines
3
/hour
Figure 1-13 (page 36)
Table 1-7
and
Table 1-8 (page 33)
and
Figure 1-14 (page 37)
for sample
for

Advertisement

Table of Contents
loading

Table of Contents