3. Attach the UPS to a power source.
4. Connect the components to the Power Distribution Unit (PDU):
5. Quorum server
6. NAS servers
44
Symmetra RM UPS:
— If the planned power load is less than or equal to 5 kVA, plug the line into an
appropriate outlet.
— If the planned power load is greater than 5 kVA, a qualified electrician must hard-wire
the input power.
Symmetra UPS:
— Regardless of the power load, a qualified electrician must hard-wire the input power.
a. Connect the power cables of the components in each rack to the PDU strip on the rack
as shown in the diagrams in
on page 9.
b. Plug the PDU into the Power Distribution Panel (PDP) on the UPS.
c. Power up the components one at a time, in the following sequence, to minimize
current inrush:
— UPS
— Tape library
Caution:
Do not boot the NAS server until the storage array has finished powering up. As
the array is powering up, amber and green lights will turn on and blink. When only green
lights remain on, it is safe to boot the NAS server.
HP StorageWorks NAS 8000 SAN High Availability, Solution Integration Manual (SIM)