Table of Contents
loading

Summary of Contents for HP 489183-B21 - InfiniBand DDR Switch

  • Page 1: Hp Blc 4X Ddr Infiniband Gen 2 Switch

    HP BLc 4X DDR InfiniBand Gen 2 Switch Installation Guide for HP c-Class BladeSystems HP Part Number: 5992-5296 Published: October 2008 Edition: 1.02...
  • Page 2 © Copyright 2008 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice. The only warranties for HP products and services are set forth in the express warranty statements accompanying such products and services. Nothing herein should be construed as constituting an additional warranty. HP shall not be liable for technical or editorial errors or omissions contained herein.
  • Page 3: Table Of Contents

    Table of Contents 1 Preparing for Installation....................7 1.1 Audience............................7 1.2 Documentation Resources.........................7 1.3 Kit Contents............................7 1.4 Additional Information........................7 1.5 HP BLc 4X DDR InfiniBand Gen 2 Switch Connector Bays..............8 1.6 HP BLc 4X DDR InfiniBand Gen 2 Switch LEDs................9 2 Hardware Installation....................11 2.1 Installing the HP BLc 4X DDR InfiniBand Gen 2 Switch..............11 2.1.1 Prepare the Interconnect Module Bay in the HP BladeSystem c7000 Enclosure....11 2.1.2 Install the HP BLc 4X DDR InfiniBand Gen 2 Switch into the HP BladeSystem Enclosure..12...
  • Page 4 List of Figures HP BLc 4X DDR InfiniBand Gen 2 Switch..................7 HP Onboard Administrator Screen Example.................8 HP BLc 4X DDR InfiniBand Gen 2 Switch Connector Bays............8 HP BLc 4X DDR InfiniBand Gen 2 Switch LEDs................9 Removing a Divider from the HP BladeSystem c7000 Enclosure Interconnect Module Bay..11 Installing the HP BLc 4X DDR InfiniBand Switch into a c7000 Enclosure........12 QSFP InfiniBand DDR/QDR Cable....................13 Align the InfiniBand Cable with the HP BLc 4X DDR InfiniBand Gen 2 Switch Port....13...
  • Page 5: List Of Tables

    List of Tables HP BLc 4X DDR InfiniBand Gen 2 Switch Descriptions and Status..........9...
  • Page 7: Preparing For Installation

    1 Preparing for Installation 1.1 Audience This document is intended for HP service representatives and other persons trained to install hardware options in HP BladeSystem configurations. Such persons are expected to understand the hazards of working in this environment and to take suitable precautions to minimize danger to themselves and others.
  • Page 8: Hp Blc 4X Ddr Infiniband Gen 2 Switch Connector Bays

    For specific port connections for each server blade, see the HP BladeSystem Onboard Administrator User Guide. Connections differ by server blade type. The information contained in this document explains the cabling between the HP 4X DDR InfiniBand Gen 2 Switch and the network switches. The HP Onboard Administrator screen example (see Figure 1-2) is a reference for port mapping.
  • Page 9: Hp Blc 4X Ddr Infiniband Gen 2 Switch Leds

    1.6 HP BLc 4X DDR InfiniBand Gen 2 Switch LEDs Figure 1-4 shows the LEDs and Table 1-1 describes the LEDS in the HP BLc 4X DDR InfiniBand Gen 2 Switch. Figure 1-4 HP BLc 4X DDR InfiniBand Gen 2 Switch LEDs Table 1-1 describes the callouts shown in Figure...
  • Page 11: Hardware Installation

    2 Hardware Installation This chapter contains the following sections: • Installing the HP BLc 4X DDR InfiniBand Gen 2 Switch (Section 2.1) • Installing InfiniBand cables in the HP BLc 4X DDR InfiniBand Gen 2 Switch (Section 2.2) • Cable Management (Section 2.3) •...
  • Page 12: Install The Hp Blc 4X Ddr Infiniband Gen 2 Switch Into The Hp Bladesystem Enclosure

    2.1.2 Install the HP BLc 4X DDR InfiniBand Gen 2 Switch into the HP BladeSystem Enclosure To install the HP BLc 4X DDR InfiniBand Gen 2 Switch into the HP BladeSystem c7000 enclosure, follow these steps: Slide the HP BLc 4X DDR InfiniBand Gen 2 Switch all the way into the HP BladeSystem c7000 enclosure (see callout 1 in Figure 2-2).
  • Page 13: Qsfp Infiniband Ddr/Qdr Cable

    Note: InfiniBand cables with QSFP to CX4 connectors are required when the HP BLc 4X DDR InfiniBand Gen 2 Switch uplinks to an InfiniBand spine interconnect with CX4 connectors. Figure 2-3 QSFP InfiniBand DDR/QDR Cable The following list describes the callouts shown in Figure 2-3: InfiniBand cable...
  • Page 14: Removing An Infiniband Cable From The Hp Blc 4X Ddr Infiniband Gen 2 Switch

    QSFP connector HP BLc 4X DDR InfiniBand Gen 2 Switch - port 1 InfiniBand cable Figure 2-5 InfiniBand Cable Installed in Port 1 of the HP BLc 4X DDR InfiniBand Gen 2 Switch The following list describes the callouts shown in Figure 2-5: InfiniBand cable installed in port 1 of the HP BLc 4X DDR InfiniBand Gen 2 Switch...
  • Page 15: Infiniband Subnet Management

    Note: The c-Class cable management bracket is not included in this kit and must be ordered separately. 2.4 InfiniBand Subnet Management The HP BLc 4X DDR InfiniBand Gen 2 Switch does not have an embedded subnet manager. All InfiniBand networks require a subnet manager to manage, monitor and troubleshoot the InfiniBand fabric.
  • Page 17: Removing The Hp Blc 4X Ddr Infiniband Gen 2 Switch For Service

    3 Removing the HP BLc 4X DDR InfiniBand Gen 2 Switch for Service Put the HP 10K series rack and the HP BladeSystem c7000 enclosure into a safe and stable state for component removal and bring the component to an appropriate state for removal. You must ensure that you can reach the component easily and handle it safely.
  • Page 19: Regulatory Compliance

    4.3 Modifications The FCC requires the user to be notified that any changes or modifications made to this device that are not expressly approved by Hewlett-Packard Company may void the user’s authority to operate the equipment. 4.4 Cables Connections to this device must be made with shielded cables with metallic RFI/EMI connector hoods in order to maintain compliance with FCC Rules and Regulations.
  • Page 20: Japanese Notice

    Figure 4-1 EU Declaration of Conformity Markings Hewlett-Packard GmbH, HQ-TRE, Herrenberger Strasse 140, 71034 Boeblingen, Germany 4.7 Japanese Notice Figure 4-2 Japanese Notice 4.8 Korean Notice Figure 4-3 Korean Notice Regulatory Compliance...