Boiler Manual
*
DO NOT USE BOILER DURING CONSTRUCTION
follow the requirements given on page 9. Failure to comply could result in severe personal injury, death or
substantial property damage.
Installation and service of the boiler must be performed by a qualified installer or service technician.
, read all instructions, including this manual, and any related supplements. Perform steps in the order
installing
given. Failure to comply can result in severe personal injury, death or substantial property damage.
*
Blower cover on sizes CGi 25-6 only
Series 4
Gas-Fired Water Boilers
• Installation
• Startup
Now With Built In
Low Water Cut Off Functionality
unless you provide dust-free air to the boiler area or
Part Number 550-142-302/0124
• Maintenance
• Parts
Before

Advertisement

Table of Contents
loading

Summary of Contents for Weil-McLain CGi 4 Series

  • Page 1 Series 4 Gas-Fired Water Boilers Boiler Manual • Installation • Maintenance • Startup • Parts Now With Built In Low Water Cut Off Functionality Blower cover on sizes CGi 25-6 only unless you provide dust-free air to the boiler area or DO NOT USE BOILER DURING CONSTRUCTION follow the requirements given on page 9.
  • Page 2: How It Works

    Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — How it works . . . Control module The control module responds to signals from the room thermostat, air pressure switch and boiler limit circuit to operate the boiler circulator, pilot burner, gas valve and inducer. When room thermostat calls for heat, the control module starts the system circulator and inducer.
  • Page 3 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — CGi Series 4 Gas-Fired Induced-Draft Water Boiler Part Number 550-142-302/0124...
  • Page 4: Table Of Contents

    Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Contents How it works ........... 2 Hazard definitions ..........4 Please read before proceeding ......5 1 Prepare boiler location ......... 6–11 2 Prepare boiler ..........12–13 3 Venting ............14-19 4 Water piping ..........
  • Page 5: Please Read Before Proceeding

    Therefore, • Do not use petroleum-based cleaning or sealing com- Weil-McLain equipment contaminated with saltwater or pounds in boiler system. Water seal deterioration will polluted water will no longer be covered under warranty occur, causing leakage between sections.
  • Page 6 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Prepare boiler location — codes & checklist Installations must follow these codes: • Local, state, provincial, and national codes, laws, regulations and ordi- nances. • National Fuel Gas Code, ANSI Z223.1/NFPA 54 – latest edition. •...
  • Page 7: Prepare Boiler Location

    Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Prepare boiler location — clearances Recommended SERVICE clearances Figure 1b Required MINIMUM clearances (Fig. 1a) 1. Provide clearances for cleaning and servicing the boiler and for access to controls and components. See Figure 1a for recommendations.
  • Page 8: Prepare Boiler

    Condensation can return doors, windows, exhaust fans, fireplace damage a masonry chimney. Weil-McLain dampers, and any other gas-burning appliance recommends the following to prevent pos- to their previous conditions of use.
  • Page 9 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Prepare boiler location — air contamination Refer to for products and areas which may Please review the following information on poten- Table 1 cause contaminated combustion air. tial combustion air contamination problems. To prevent potential of severe personal injury or death, check for products or areas listed below before installing boiler.
  • Page 10 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Prepare boiler location — air openings Figure 2 Air openings to interior spaces Combustion air opening location and sizing requirements depend on the clearances around the boiler. Check the boiler placement compared to Figure 1a, page 7.
  • Page 11 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Prepare boiler location — air openings Unusually tight construction of openings — the minimum areas FREE AREA given in this manual are free area (equals the Unusually tight construction means (per ANSI area, length times width of opening, after deduc- Z223.1/NFPA 54) buildings in which: tion for louver obstruction).
  • Page 12 2,000-4,500 Canada CGi-25 2.30 mm CGi-3 and CGi-5 2.55 mm 1.60 mm 1.45 mm CGi-4, CGi-6 - CGi-8 2.70 mm 1.65 mm Note 1: For elevations above 2,000 feet, contact your local Weil-McLain sales office for details. Part Number 550-142-302/0124...
  • Page 13 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Prepare boiler — pressure test Hydrostatic pressure test 4. Close shutoff valves. 5. Slowly reopen boiler drain valve until test Pressure test boiler attaching water or gas before pressure on the pressure/temperature gauge piping (except as noted below) or electrical supply.
  • Page 14: Venting

    Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Venting — general information CGi venting methods — Chimney draft or Direct exhaust Chimney draft venting Direct exhaust — vertical or sidewall Chimney draft venting uses the natural draft pro- Direct exhaust venting uses inside combustion air vided by a vertical vent or chimney.
  • Page 15 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Venting — Direct exhaust — components Obtain vent system components Table 4 Maximum vent length 1. The following special gas vent systems comply with UL-1738 and ULC-S636 standards and are certified by CSA as the only Max.
  • Page 16 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Venting — direct exhaust — vent starter 1. Select a vent pipe manufacturer and obtain 3. Follow all applicable national, state, local or all vent components needed, based on boiler provincial codes when venting the CGi boiler. location and venting method.
  • Page 17 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Venting — direct exhaust — termination The vent termination must be located to meet all requirements below (also applies to vertical vent terminations). The minimum distance from adjacent public walkways, adjacent buildings, openable windows and building in the National Fuel Gas Code, ANSI Z223.1/NFPA 54 –...
  • Page 18 • Vent is sloped toward termination as shown in dotted lines in Figure 14. • The vent is installed per Weil-McLain and vent manufacturer’s instructions. • Condensate drip page from such vents may ac- cumulate on the ground below. Consider traffic in the area to avoid hazard due to ice accumulation.
  • Page 19 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Venting — direct exhaust — installation (cont.) Using any termination other than one of those Figure 15 Sidewall termination shown could cause nuisance outages and loss of heat, resulting in substantial property damage. Part Number 550-142-302/0124...
  • Page 20: Water Piping

    Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Water piping — general information General piping information Circulator If installation is to comply with ASME or Canadian requirements, The circulator is shipped loose (wiring pre-attached an additional maybe needed. Install control in to boiler) to allow you to locate it either in the re- high temperature limit supply piping between boiler and isolation valve.
  • Page 21 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Water piping — single-zone system Undersized expansion tanks cause system water to be lost from relief valve and makeup water to be added through fill valve. Eventual section failure can result. Diaphragm-type or bladder- Closed-type expansion tank type expansion tank...
  • Page 22 Instead, provide controls and piping which can regulate the boiler return water temperature at no less than 130°F regardless of system supply temperature. Contact your Weil-McLain representative for suggested piping and control methods. Failure to prevent cold return water temperature to the boiler could cause corrosion damage to the sections or burners, resulting in possible severe personal injury, death or substantial property damage.1...
  • Page 23 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Water piping — multiple zones (continued) Figure 18 Zoning with circulators Figure 19 Zoning with zone valves — return water 130°F or higher. — return water 130°F or higher. Boiler isolation (balancing) Automatic air vent (with diaphragm-type expansion tank), or valves connect to tank fitting (closed-type expansion tank).
  • Page 24 Instead, provide controls and piping which can regulate the boiler return water temperature at no less than 130°F regardless of system supply tem- perature. Contact your Weil-McLain representative for suggested piping and control methods. Failure to prevent cold return water temperature to the boiler could cause corrosion damage to the sections or burners, resulting in possible severe personal injury, death or substantial property damage.
  • Page 25 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Piping — low temperature systems (continued) Figure 20 Primary/secondary piping Figure 21 Primary/secondary piping Zoning with circulators Zoning with zone valves 1 Boiler isolation (balancing) valves 9 Relief valve 10 Automatic air vent (with diaphragm-type expansion tank), 2 Flow/check valve or connect to tank fitting (closed-type expansion tank).
  • Page 26 Instead, provide controls and piping which can regulate the boiler return water temperature at no less than 130°F regardless of system supply temperature. Contact your Weil-McLain representative for suggested pip- ing and control methods. Failure to prevent cold return water temperature to the boiler could cause cor- rosion damage to the sections or burners, resulting in possible severe personal injury, death or substantial property damage.
  • Page 27 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Piping — low temperature systems (continued) Figure 22 Boiler-bypass piping — Zoning with Figure 23 Boiler-bypass piping — Zoning with circulators — (Alternative to primary/ zone valves — (Alternative to primary/ secondary piping Figures 20 and 21) secondary piping Figures 20 and 21) Boiler isolation (balancing) valves...
  • Page 28 130°F temperature. Contact your Weil-McLain representative for suggested piping and control methods. Failure to to the boiler could cause corrosion prevent cold return water temperature damage to the sections or burners, resulting in possible severe personal injury, death or substantial property damage.
  • Page 29 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Piping — low temperature systems (continued) Figure 24 System-bypass piping — Zoning with zone valve or circulators, return water 130°F or higher — (Alternative to boiler- bypass piping Figures 22 and 23) 3 System or zone circulator 7 System temperature valves (see instructions to the left for adjusting valves)
  • Page 30: Gas Piping

    Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Gas piping Natural Gas: Connecting gas supply piping to boiler 1. Refer to for pipe length and diameter. Base on Table 7 rated boiler input (divide by 1,000 to obtain cubic feet 1.
  • Page 31: Field Wiring

    Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Field wiring For your safety, turn off electrical power sup- plus gas valve current. See information on wiring diagram ply at service entrance panel before making as shown in Figure 32, page 39. For other devices, refer any electrical connections to avoid possible to manufacturer’s specifications.
  • Page 32: Start-Up

    Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Start-up — preparation Check for gas leaks Determine if water treatment is needed Before starting the boiler, and Do not use petroleum-based cleaning or sealing during initial operation, smell in boiler system. Severe damage to compounds near the floor and around the boiler will occur, resulting in substantial property...
  • Page 33 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Start-up — preparation (continued) Fill the system with water Inspect system water piping 1. Close manual and automatic and boiler drain cock. air vents After filling the boiler and system with water, throughout the system for leaks.
  • Page 34 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Start-up — operate boiler proceed with boiler operation unless boiler and system have been filled with water and all DO NOT instructions and procedures of previous manual sections have been completed. Failure to do so could result in severe personal injury, death or substantial property damage.
  • Page 35 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Start-up — operate boiler (continued) Start the boiler • Follow the from Section Main burner flame ( Operating instructions Figure 29 start the boiler. PROPER main burner flame characteristics • if boiler fails to start. Section 7c 1.
  • Page 36: Check-Out Procedure - Checklist

    Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Check-out procedure — checklist e. Pilot will relight, flame sensing element will sense Boiler and heat distribution units filled with water? pilot flame and main burners will reignite. Automatic air vent, if used, open one full turn? Set limit control(s) to system temperature require- Air purged from system? ments.
  • Page 37: Department Of Energy Compliance

    Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Department of Energy – Compliance This boiler is equipped with a control system that automatically adjusts a time delay period to turn on the boiler during a call for heat. This is accomplished by circulating available hot water in the system while measuring water boiler water temperature changes.
  • Page 38 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Operation — sequence (continued) — The circulator continues to operate. room thermostat setting to stop call for heat. Thermostat is satisfied — Pilot and main gas Lower valves are closed — Inducer operates for 15-second postpurge — Circulator is shut off. 8.
  • Page 39 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Operation — wiring diagrams Figure 31 Schematic wiring diagram Part Number 550-142-302/0124...
  • Page 40 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Operation — wiring diagrams (continued) Figure 32 Ladder wiring diagram Part Number 550-142-302/0124...
  • Page 41 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Operating instructions CGi-25 thru -6 • Spark pilot • Natural or propane gas • Gas valve: Honeywell VR8204/VR8304 Part Number 550-142-302/0124...
  • Page 42 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Operating instructions • Spark pilot • Natural or propane gas CGi-25 thru -6 • Gas valve: White-Rodgers 36E Part Number 550-142-302/0124...
  • Page 43 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Operating instructions • Spark pilot • Natural or propane gas CGi-25 thru -8 • Gas valve: White-Rodgers 36C Part Number 550-142-302/0124...
  • Page 44: Service And Maintenance

    Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Service and maintenance — schedule VERIFY PROPER OPERATION AFTER SERVICING Table 8 Service and maintenance schedules Service technician Owner maintenance (see following pages for instructions) (see CGi User’s Information Manual for instructions) •...
  • Page 45 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Service and maintenance — annual start-up Air openings 1. Verify that combustion and ventilation air open- The boiler should be ings to the boiler room and/or building are open inspected and started an- unobstructed , at the beginning of the heating season, nually...
  • Page 46 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Service & maintenance – annual start-up (cont.) Inspect . . . 4. Reinstall components, starting with the burner tray, then the pilot bracket assembly, burner baffle, and air inlet top and Burners and base front panels.
  • Page 47 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Service & maintenance – annual start-up (cont.) Check/test . . . type. See Section of this manual for suggested best location of expansion tanks and air elimina- tors. Gas piping — located above highest radiator or Open-type baseboard unit, usually in the attic or closet.
  • Page 48 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Service & maintenance – annual start-up (cont.) Review with owner Safety relief valves should be reinspected , by a AT LEAST ONCE EVERY THREE YEARS licensed plumbing contractor or authorized 1. Review the with the User’s Information Manual inspection agency, to ensure that the prod-...
  • Page 49 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Troubleshooting — procedure Check the following: Label all wires prior to dis- connection when servicing 1. Wire connectors to control module are securely plugged in at controls. Wiring errors can module and originating control. cause improper and dan- 2.
  • Page 50: Troubleshooting

    — remove tees and reinstall hoses to air pressure switch. Table 10 Temperature/LWCO sensor resistance values Table 9 Pressure switch setpoint (for elevations above 2,000 ft., contact your local Weil-McLain Technical Service office for details.) Sensor resistance values Boiler model number Inches W.C. Sensor ohms Sensor ohms Temp.
  • Page 51 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Troubleshooting — components (continued) Control indicator lights — The information on this page and pages 52 through 60 ap- LOCKOUT modes ply only to spark-ignited pilot See Charts 1 through 8 in this section for detailed trouble- CGi boilers.
  • Page 52 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Troubleshooting — components (continued) Figure 38 Control module connections Part Number 550-142-302/0124...
  • Page 53 • Replace transformer. licensed electrician. • Replace control module. • Retest and check for • If problem persists, contact back feed of voltage from • Boiler should now • Retest. your Weil-McLain Technical system wiring. operate normally. support. Part Number 550-142-302/0124...
  • Page 54 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Troubleshooting — control module lights (cont.) CHART 2 –– TSTAT CIRC & POWER light flashing –– Usually indicates 48 VAC on thermostat circuit (stray voltage) –– Electrical shock hazard — Wherever you see ▲ TURN OFF POWER ▲, follow the instructions. Failure to follow instructions could result in severe personal injury, death or substantial property damage.
  • Page 55 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Troubleshooting — control module lights (cont.) CHART 3 –– PURGE & POWER light flashing –– Usually indicates pressure switch stuck closed or failed to make within 5 minutes –– Electrical shock hazard — Wherever you see ▲ TURN OFF POWER ▲, follow the instructions. Failure to follow instructions could result in severe personal injury, death or substantial property damage.
  • Page 56 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Troubleshooting — control module lights (cont.) CHART 4 –– FLAME & POWER light flashing –– Usually indicates flame sensed when it shouldn’t be there –– Electrical shock hazard — Wherever you see ▲ TURN OFF POWER ▲, follow the instructions. Failure to follow instructions could result in severe personal injury, death or substantial property damage.
  • Page 57 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Troubleshooting — control module lights (cont.) CHART 5 –– PURGE light flashing and POWER light on steady –– Usually indicates pressure switch opened during run cycle –– –– May also be caused by wind gusts in excess of 31 mph for non-direct vent sidewall-vented boilers –– Electrical shock hazard —...
  • Page 58 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Troubleshooting — control module lights (cont.) CHART 6 –– FLAME light flashing and Power light on steady Also –– Troubleshooting failure to establish main flame. Electrical shock hazard — Wherever you see ▲ TURN OFF POWER ▲, follow the instructions. Failure to follow instructions could result in severe personal injury, death or substantial property damage.
  • Page 59 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Troubleshooting — control module lights (cont.) Troubleshooting LWCO and POWER light Solid CHART 7 –– and/or “LCO” shown on display Electrical shock hazard — Wherever you see ▲ TURN OFF POWER ▲, follow the instructions. Failure to follow instructions could result in severe personal injury, death or substantial property damage.
  • Page 60 10.0” w.c. on propane? • See Figure 30, page 38 continuity – for normal sequence of operation. Is switch closed? • Contact Weil-McLain • Check heat loss calculation Technical support or versus boiler size. replace gas valve. • Replace rollout switch.
  • Page 61 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Notes Part Number 550-142-302/0124...
  • Page 62: Replacement Parts

    Trim ................. 67 Controls ................68 Replacement parts must be purchased through a local Weil-McLain distributor. When ordering, specify boiler model and size and include description and part number of replacement part. Results from using modified or other manufactured parts will not be covered by warranty and may damage boiler or impair operation.
  • Page 63 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Replacement parts — section assembly Figure 39 Section assembly Item Description Weil-McLain Item Description Weil-McLain part number part number Washer, 7⁄16” (1 per tie rod) End section, left hand, 51124 311-103-851...
  • Page 64 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Replacement parts — base Figure 40 Base assembly Weil-McLain Item Description part number Base assembly kit CGi-25 & CGi-3 381-354-337 (includes base panels items 1, 2, 3, 4, 5, 6 and 7)
  • Page 65 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Replacement parts — base (continued) Part Number 550-142-302/0124...
  • Page 66 Panel, right side, Panel, top front, Panel, top rear, 2 x 4 with insulation with insulation with insulation with insulation Natural Gas Propane Gas Boiler Boiler Weil-McLain part number Model Model CGi-25 (Available at 381-359-215 381-359-222 381-359-229 381-359-230 381-359-242 CGi-25 CGi-3...
  • Page 67 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Replacement parts — trim Figure 42 Trim assembly Item Description Weil-McLain number part number Pressure relief valve, ASME, 30 PSIG, ¾” male inlet 383-500-095 (Fittings shown are factory-installed on boiler.) Combination pressure-temperature gauge, 3Z\,” diameter, short shank 380-000-000 (Fittings shown are shipped loose with boiler.)
  • Page 68 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Replacement parts — controls Figure 43 Gas control assembly Item Description Boiler model Weil-McLain number part number Natural gas components Gas valve, ½” x ½” CGi-25 thru -6 511-044-381 511-044-353 ¾...
  • Page 69: Dimensions And Ratings

    Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Dimensions Figure 44 Dimensional drawing Boiler Supply Return “W” model tapping tapping connection size manifold size Jacket number width (inches NPT) (inches NPT) Note 3 Note 3 (inches NPT) (inches NPT) (inches) CGi-25 1 ¼...
  • Page 70 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Ratings Table 11 Boiler ratings AHRI Certified Ratings Boiler Boiler Ratings model 0 - 2,000 feet 2,000 - 4,500 feet Heating Seasonal water Vent number Altitude Altitude Capacity Efficiency (water) content size Btuh Btuh...
  • Page 71: Handling Ceramic Fiber And Fiberglass Materials

    Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Handling ceramic fiber and fiberglass materials REMOVAL OF COMBUSTION CHAMBER REMOVAL OF FIBERGLASS WOOL LINING OR BASE PANELS The combustion chamber lining INSTALLATION OF FIBERGLASS or base insulation panels in this WOOL, product contain ceramic fiber materials that have been identified...
  • Page 72 Boiler Manual SERIES 4 — GAS-FIRED WATER BOILER — Part Number 550-142-302/0124...

This manual is also suitable for:

Cgi-25Cgi-3Cgi-4Cgi-5Cgi-6Cgi-7 ... Show all

Table of Contents