5 Installation

Only expert, qualified personnel must carry out the installation, in full compliance with the applicable law.
5.1 Preliminary checks
Before actually installing the gate operator, your are required to:
• Check that the leaf is rigid and compact and that the rollers are in good working order and properly greased
• The gate track must be firmly set into the ground, above ground along its entire length and free of any foreign objects
(debris) that may hamper the gate's movement
• The top non-pinch rollers must not cause any friction
• See to installing physical stops at fully-opened and fully-closed positions and the power supply line trench as per the
standard installation
• Make sure that the spot were the operator is mounted is located in an area that is protects it from any impacts, and that
the mounting surface be solid
• See to installing a suitable all-pole disconnector switch, with power isolation contacts more than 3mm apart from each
other
Connections inside of the casing made to provide continuity to the protection circuit are allowed, as long as they
have additional isolation compared to other internal conductive parts
• Set up suitable tubing and trenching to allow for electrical cables to pass, making sure they are free from any potential
mechanical damage.
5.2 Tools and materials
Make sure you have all the tools and materials handy, to carry out the installation in total safety, according to the laws
inforce. Below is a drawing of the tools you will need to install the operator.
5.3 Cable list and minimun thickness
Connections
120V- 2F power supply
120V flashing lamp
Photoelectric cells TX
Photoelectric cells RX
24V power supply accessory
Control button
Antenna connection
Note: An evaluation of the size of the cables with lengths other than the data in the table must be made based on the
effective absorption of the connected devices and according to to the local electrical code standards. For connections
that require several loads on the same line (sequential), the size given on the table must be re-evaluated based on actual
absorption and distances.
8
Type of cable
Length of cable 3 < 32ft
3 x 14AWG
2 x 18AWG
2 x 20AWG
UL LISTED
CABLE/WIRE
4 x 18AWG
2 x 18AWG
2 x 20AWG
RG58
Length of cable 32 < 65ft
3 x 14AWG
2 x 18AWG
2 x 20AWG
4 x 18AWG
2 x 18AWG
2 x 20AWG
max. 32 ft
Length of cable 65 < 100ft
3 x 14AWG
2 x 18AWG
2 x 20AWG
4 x 18AWG
2 x 18AWG
2 x 20AWG

Advertisement