Inboard E-ring
Figure 8.49
E-ring
Figure 8.50
NOTE: It may be necessary to reach in behind the dash from the left side of the tractor and guide the harness
connector out of the hole between the frame and the dash support on the right side of the tractor.
13.
Connect the actuator harness to the main harness.
14.
Operate the deck lift through its full range of travel.
15.
Install the deck by following the procedures described in the deck removal section of this chapter.
16.
Check the deck for levelness and pitch.
17.
Test run the tractor in a safe area before returning it to service.
8.
Disconnect the deck lift actuator from the deck lift
shaft:
8a. Remove the inboard E-ring from the pin that
connects the lift actuator to the lift shaft con-
necting arm. See Figure 8.49.
8b. Remove the pin by sliding it out to the left.
9.
Disconnect the deck lift actuator from the frame:
9a. Remove the left E-ring from the pin that con-
nects the lift actuator to the frame.
See Figure 8.50.
9b. While supporting the actuator, slide the pin far
enough to the right for the actuator to clear it.
10. Install the actuator by following steps 8 and 9 in
reverse order.
11. Tie the end of the string that was fished through the
dash onto the actuator harness.
12. Pull the string until the harness has been routed back
through the dash.