1MRK511447-UEN Rev. E
Section 10
10.1
Commissioning tests
During commissioning all protection functions shall be verified with the setting values used at each
plant. The commissioning tests must include verification of all circuits by green-lining the circuit
diagrams and the configuration diagrams for the used functions.
Further, the settings for protection functions are tested and recorded carefully as outlined for the
future periodic maintenance tests.
Finally, final trip tests must be performed. This involves activation of protection functions or tripping
outputs with the circuit breaker closed and the tripping of the breaker verified. When several breakers
are involved, each breaker must be checked individually and it must be verified that the other
involved breakers are not tripped at the same time.
10.2
Periodic maintenance tests
The periodicity of all tests depends on several factors, for example the importance of the installation,
environmental conditions, simple or complex equipment, static or electromechanical IEDs, and so on.
The normal maintenance praxis of the user should be followed. However, Hitachi Energy's
recommendation is as follows:
Every second to third year
•
Visual inspection of all equipment.
•
Removal of dust on ventilation louvres and IEDs if necessary.
•
Periodic maintenance test for protection IEDs of object where no redundant protections are
provided.
Every four to six years
•
Periodic maintenance test for protection IEDs of objects with redundant protection system.
10.2.1
Visual inspection
Prior to testing, the protection IEDs should be inspected to detect any visible damage that may have
occurred (for example, dirt or moisture deposits, overheating).
Make sure that all IEDs are equipped with covers.
10.2.2
Maintenance tests
To be made after the first half year of service, then with the cycle as proposed above and after any
suspected maloperation or change of the IED setting.
Switchgear control unit SAM600-IO
Commissioning manual
Commissioning and maintenance of
the fault clearing system
First maintenance test should always be carried out after the first half year of service.
When protection IEDs are combined with built-in control, the test interval can be
increased drastically, up to for instance 15 years, because the IED continuously reads
service values, operates the breakers, and so on.
© 2017 - 2023 Hitachi Energy. All rights reserved
Commissioning and maintenance of the fault clearing system