Meter Body Installation Tasks; Handling; Flow Direction; Gaskets - Emerson Rosemount 8600D Series Reference Manual

Vortex flowmeter
Hide thumbs Also See for Rosemount 8600D Series:
Table of Contents

Advertisement

Reference Manual
00809-0100-4860, Rev BC
2.5

Meter body installation tasks

The installation tasks include detailed mechanical and electrical
installation procedures.
2.5.1

Handling

Handle all parts carefully to prevent damage. Whenever possible, transport the system to the
installation site in the original shipping containers. Keep the shipping plugs in the conduit
connections until you are ready to connect and seal them.
Note
Do not lift the flowmeter by the transmitter. Lift the meter by the meter body. Lifting supports
can be tied around the meter body as illustrated below if necessary.
2.5.2

Flow direction

Mount the meter body so the FORWARD end of the flow arrow, shown on the meter body,
points in the direction of the flow in the pipe.
2.5.3

Gaskets

The Rosemount 8600D requires flange gaskets supplied by the user, and sensor gaskets
supplied with the meter. Be sure to select gasket material that is compatible with the process
fluid and pressure ratings of the specific installation.
Note
Ensure that the inside diameter of the flange gasket is larger than the inside
diameter of the flowmeter and adjacent piping. If gasket material extends into the flow stream,
it will disturb the flow and cause inaccurate measurements.
Installation