There are a number of important steps required to set up your generator for initial use. These
steps are:
1. Unpacking & delivery inspection.
2. Planning the power load to stay within the generator's rated
capacity.
3. Setting up generator for the type of power generation you need:
a. portable power source, or
b. connected to a building as a back-up power source.
4. Selecting a site for using the generator.
5. Grounding.
Each of these steps is discussed in detail below:
You should inspect the generator immediately after you receive delivery.
See the "Machine Component Identification" section of this manual for a
diagram of the generator and its components.
If you have missing or
Plan your power load so that you do not exceed the generator's rated capacity.
See the "Power Load Planning & Management" section of this manual to review how to plan and
manage power loads for the generator.
Installation / Initial Set-Up
Steps for Installation / Initial Set-Up
1. Unpacking & Delivery Inspection
components, contact Product Support at 1-800-270-0810.
damaged
2. Planning the Power Load
12