1. Upon a call for heat, the gas pressure switch(es) must be closed.
2. Once the gas pressure switch(es) are closed, the control turns
on the appropriate pumps (system and boiler pumps for space
heating, DHW pump for DHW). The flow switch and/or LWCO
must close.
3. The control turns on power to the louver relay. The louver
proving switch, and blocked drain switch must close.
4. The control starts the prepurge cycle by initiating the blower.
5. The control starts the trial for ignition by firing the spark
electrode and opening the gas valve.
6. If flame is not detected after the sparking ends, the control will
perform a postpurge, then start another prepurge cycle and try
to light the burner again. The control will perform a total of 4
attempts before locking out.