Test Operation - Daikin RZQ200B8W1B Installation Manual

Table of Contents

Advertisement

Led state
Throughout the manual the state of the leds is indicated as follows:
x
OFF
w
ON
c
blinking
Setting the dip switches
What to set with dip switch DS1
3
LOW NOISE OPERATION LEVEL SETTING (
(
OFF
= not installed = factory setting)
4
HIGH STATIC PRESSURE SETTING
5
AUTOMATIC LOW NOISE OPERATION AT NIGHT TIME
6
POWER CONSUMPTION LIMITATION SETTING (
1, 2, 7, 8
NOT APPLICABLE
DO NOT CHANGE THE FACTORY SETTING.
Setting the push button switch (BS1~5)
Function of the push button switch which is located on the outdoor
unit PCB (A1P):
TEST:
MODE
HWL:
H1P
H2P
H3P
BS1
BS2
BS3
MODE
SET
RETURN
For changing the set mode
BS1 MODE
For field setting
BS2 SET
For field setting
BS3 RETURN
For test operation
BS4 TEST
For forced defrost or pump down
BS5 FORCED DEF
Setting the mode 2
The set mode can be changed by pressing the
5 seconds. The setting mode will change to setting mode 2 and the
w
H1P led will be ON
.
NOTE
If you get confused in the middle of the setting
process, push the
returns to setting mode 2 (H1P led is ON
Exiting mode 2
When all settings are finished and the operation did start according to
the setting, push the
BS1 MODE
Installation manual
15
(See figure 21)
L.N.O.P
DEMAND
HIGH STATIC
LN.O.P
L.N.O.P DEMAND
PRESSURE
NGHT
H4P
H5P
H6P
H7P
BS4
BS5
FORCED
TEST
DEF
BS1 MODE
button once. Then it
BS1 MODE
w
).
button once to exit the mode 2.

9.4. Test operation

NOTE
After turning on the power supply, the unit cannot be
started until the H2P initialisation led goes off
(maximum 12 minutes).
Check the stop valves
Make sure to open the gas and liquid line stop valves.
For details on test operation, refer to the indoor unit installation
manual.
)
Pre-run checks
)
Electrical wiring
Inter-unit wiring
Ground wire
Refrigerant piping
Extra refrigerant
1
Make sure the liquid and gas shut-off valves are open.
button for
B
Be sure to close the frontside panel before operation, as not
doing so can cause electric shock.
-
The refrigerant pressure may not rise, even if the shut-off
valve is opened after an air purge is performed using a
vacuum pump.
This is because the indoor unit refrigerant piping is closed off
with electric valves inside. This will not create any problems
during operation.
2
To protect the compressor, make sure to turn on the power
supply 6 hours before starting operation.
Test operation from remote controller
1
Be sure to set it to cooling and press the operation switch.
2
Press the inspection/test-run switch on the remote control to put
the machine into test-run mode.
Items to check
Is the wiring as mentioned on the wiring
diagram?
Make sure no wiring has been forgotten
and that there are no missing phases or
reverse phases.
Is the unit properly grounded?
Are any of the wiring attachment screws
loose?
Is the insulation resistance at least 2 MΩ?
-
Use a 500 V mega-tester when
measuring insulation.
-
Do not use a mega-tester for circuits
which are not 230 V.
Is the size of the piping appropriate?
Is the insulation material for the piping
attached securely?
Are both the liquid and gas pipes
insulated?
Are the shut-off valves for both the liquid
side and the gas side open?
Did you write down the extra refrigerant
and the refrigerant piping length?
Opening direction
A
Liquid side
A
B
Gas side
Remove the cap and turn
counterclockwise with a
hex wrench until it stops
RZQ200+250B8W1B
Split system air conditioner
4PW25544-1A