Installation of drain piping
Install the drain piping as shown in figure and take measures against
condensation. Improperly rigged piping could lead to leaks and
eventually wet furniture and belongings.
1-1.5 m
1
Hanging bar
Install the drain pipes.
-
Keep piping as short as possible and slope it downwards at a
gradient of at least 1/100 so that air may not remain trapped
inside the pipe.
-
Keep pipe size equal to or greater than that of the connecting
pipe (vinyl pipe of 25 mm nominal diameter and 32 mm outer
diameter).
-
Push the supplied drain hose as far as possible over the
drain socket.
1
1
Drain socket (attached to the unit)
2
Drain hose (supplied with the unit)
-
Tighten the metal clamp until the screw head is less than
4 mm from the metal clamp part as indicated in the
illustration.
-
After the testing of drain piping is finished, attach the drain
sealing pad (4) supplied with the unit over the uncovered part
of the drain socket (= between drain hose and unit body).
4
1
3
1
Drain socket (attached to the unit)
2
Drain hose (supplied with the unit)
3
Metal clamp (supplied with the unit)
4
Drain sealing pad (supplied with the unit)
5
Large sealing pad (supplied with the unit)
6
Drain piping (field supply)
-
Wrap the supplied large sealing pad over the metal clamp
and drain hose to insulate and fix it with clamps.
-
Insulate the complete drain piping inside the building (field
supply).
-
If the drain hose cannot be sufficiently set on a slope, fit the
hose with drain raising piping (field supply).
Installation and operation manual
5
1
2
A-A'
5
4 mm
A
A'
2
6
How to perform piping
1
Ceiling slab
2
Hanger bracket
3
Adjustable range
4
Drain raising pipe (nominal diameter of vinyl pipe = 25 mm)
5
Drain hose (supplied with the unit)
6
Clamp metal (supplied with the unit)
1
Connect the drain hose to the drain raising pipes, and insulate
them.
2
Connect the drain hose to the drain outlet on the indoor unit, and
tighten it with the clamp.
Precautions
-
Install the drain raising pipes at a height of less than 675 mm.
-
Install the drain raising pipes at a right angle to the indoor
unit and no more than 300 mm from the unit.
-
To prevent air bubbles, install the drain hose level or slightly
tilted up (≤75 mm).
NOTE
Testing of drain piping
After piping work is finished, check if drainage flows smoothly.
Add approximately 1 l of water gradually through the air
discharge outlet.
Method of adding water. See
1
Plastic watering can (tube should be about 100 mm long)
2
Service drain outlet (with rubber plug) (Use this outlet to
drain water from the drain pan)
3
Drain pump location
4
Drain pipe
5
Drain socket (water flow view point)
Check the drainage flow.
3
In case electric wiring work is finished
5
Check drainage flow during COOL running, explained in
1
2
operation" on page
In case electric wiring work is not finished
-
Remove the control box lid. Connect the power supply
firmly to the terminal. See
-
Reattach the control box lid and turn on the power.
-
Do not touch the drain pump. It may result in electric
shock.
1
2
3
4
5
6
7
8
9
10
(See figure 7)
The incline of attached drain hose should be
75 mm or less so that the drain socket does
not have to withstand additional force.
To ensure a downward slope of 1:100, install
hanging bars every 1 to 1.5 m.
When unifying multiple drain pipes, install the
pipes as shown in
figure
9. Select converging
drain pipes whose gauge is suitable for the
operating capacity of the unit.
1
T-joint converging drain pipes
figure
11.
9.
figure
10.
Control box lid
Power supply wiring
Power supply terminal block
Clamp (field supply)
Unit transmission wiring
Terminal block for transmission wiring
Opening for cables
Wiring diagram label
(on the back side of the control box lid)
Earth cable
Remote controller wiring
VRV System air conditioners
"Test
FXFQ20~125P8VEB
4PW44997-1

Advertisement

Table of Contents
loading

Table of Contents