Receiving Inspection; Hanging/Installation Requirements - Greenheck XG-RT-500 Installation, Operation And Maintenance Manual

Round retrofit vav terminals

Advertisement

Receiving Inspection

Prior to removing the shipping materials, visually inspect the
packing materials. There should be a black plastic strip wrapped
in the clear plastic stretch wrap. If this black plastic strip is miss-
ing, the shipment may have been repacked by the shipper and
you should make a note of this on the shipping documents and
inform the delivering carrier.
After unpacking the terminals, check for shipping damage. If any
shipping damage is found, report it immediately to the delivering
carrier.
Always store the product in a clean dry location prior to installa-
tion.
Units with controls are not recommended for use in ambient
temperatures greater than 95º F. For protection of controls, do
not store in temperatures above 135ºF.
Caution: Do not use the flow sensor, connecting tubing or
damper shaft as a lift point. Damage to the components
may result.

Hanging/Installation Requirements

Unless local building codes require hangers, the basic
5
XG-Round Retrofit Air Terminals may be light enough to be
supported by the ductwork itself.
Straps or the method prescribed for round duct on the job
5
specification may be used. (See figure 1)
Trapeze hangers or the method prescribed for round duct on
5
the job specification may be used.
(See figure 2)
Note:
XG-Round Retrofit Air Terminals are not designed nor
suitable for outdoor use.
In advance of startup, verify all electrical connections are
tight and that the correct voltage is supplied to the XG-
Round Retrofit Air Terminal per the voltage listed on the
label. If factory supplied controls are present, review all wiring
diagrams for complete working knowledge.
Figure 1 Hanging Straps
XG-Round Retrofit VAV Terminals Rev 2