9
Installing the Hose between
the Upper T-fitting and the Ball
Valve
Parts needed for this procedure:
1
Hose clamp
1
Retainer
Procedure
Note: To insert the barbed fitting into the hose more easily,
apply a light coat of a non-petroleum-based lubricant, such as
vegetable oil to the barbed end of the fitting.
1. Install the reducer hub at the end of the transfer hose
into the inboard port of the upper T-fitting
Figure 41
1. 90° hub fitting
2. Transfer hose 1.9 x 61 cm
(3/4 x 24 inch)
2. Secure the reducer hub to the T-fitting with a retainer
(Figure
41).
3. Assemble the free end of the transfer hose over the
straight-barbed fitting at the inboard side of the ball
valve
(Figure
42).
(Figure
3. T-fitting
4. Retainer
1. Transfer hose 1.9 x 61 cm
(3/4 x 24 inch)
2. Hose clamp
4. Secure the hose to the barbed fitting with a hose clamp
(Figure
42).
10
41).
Installing the Hose between
the Ball Valve and the 4-Way
Valve
Parts needed for this procedure:
1
Hose 1.9 x 76 cm (3/4 x 30 inch)
2
Hose clamp
Procedure
Note: To insert the barbed fitting into the hose more easily,
apply a light coat of a non-petroleum-based lubricant, such as
vegetable oil to the barbed end of the fitting.
1. Assemble the end of the Hose 1.9 x 76 cm (3/4 x 30
inch) over the straight-barbed fitting at the outboard
side of the ball valve
21
Figure 42
3. Straight-barbed fitting (ball
valve)
(Figure
43).