INSTALLATION CHECKLIST

Note: Use and complete this checklist before lighting the heater.
Correct any conditions that do not meet these instructions.
WATER HEATER LOCATION
Centrally located with the water piping system. Located
as close to gas piping and vent pipe system as possible.
Located indoors and in a vertical position. Protected
from freezing temperatures.
Proper clearances from combustible surfaces main-
tained and not installed directly on a carpeted floor.
Provisions made to protect the area from water dam-
age. Metal drain pan installed and piped to an adequate
drain.
Installation area free of corrosive elements and flam-
mable material.
Sufficient room to service the water heater.
GAS SUPPLY AND PIPING
Gas supply is the same type as listed on the water
heater data plate.
Gas line equipped with shut-off valve, union and sedi-
ment trap.
Approved pipe joint compound used.
Adequate pipe size and of approved material.
Chloride-free soap and water solution or other approved
means used to check all connections and fittings for
possible gas leaks.
VENT PIPE SYSTEM
Vent pipe and fittings of approved material.
Acceptable size, length and number of elbows on
exhaust vent system.
Installed in accordance with prevailing provisions of
local codes, or in the absence of such, the latest edition
of Natural Gas and Propane Installation Code B149.1.
Horizontal piping slopes at an upward pitch of 3 mm
(1/8") rise per 1.5 m (5') away from the water heater.
Not obstructed in any way.
Means installed to collect, neutralize (if required) and
dispose of condensate.
VENT TERMINATION
Horizontal
300 mm (12") min. above grade/snow level.
Away from corners, other vents, windows etc.
Vertical
Air Intake and Exhaust terminations 450 mm (18") min.
above roof/snow level.
WATER SYSTEM PIPING
Temperature and Pressure relief valve properly installed
with a discharge line run to an open drain and protected
from freezing.
All piping properly installed and free of leaks.
Heater completely filled with water.
Closed system pressure build-up precautions installed.
Thermostatic Mixing Valves installed at each point-of-
use.
ELECTRICAL CONNECTIONS
Unit connected to a 120V electrical supply. A dedicated
circuit is preferred. Do not use a GFI outlet.
Proper polarity.
Water heater properly grounded.
Installed in accordance with prevailing provisions of
local codes, or in the absence of such, the latest edition
of Canadian Electrical Code (CSA C22.1), Part I.
After all actions on checklist are checked/completed, read the
Lighting Instructions and proceed with lighting the heater.
41

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents