Start-Up And Putting The Device Back Into Operation; Starting Up The Plant - Samson 2357-3 Mounting And Operating Instructions

Pressure build-up regulator
Table of Contents

Advertisement

Start-up
6.1 Start-up and putting the
device back into operation
1. Depending on the field of application,
allow the regulator to cool down or
warm up to reach ambient temperature
before start up.
2. Slowly open the shut-off valves in the
pipeline. Slowly opening these valves
prevents a sudden surge in pressure and
high flow velocities which can damage
the valve.
3. Check the regulator to ensure it functions
properly.
6-2

6.2 Starting up the plant

1. Start up the regulator after mounting all
parts.
2. Open the shut-off valves slowly prefera-
bly starting from the upstream pressure
side. Afterwards, open all the valves on
the consumer side (downstream of the
regulator).
3. Fill the plant slowly with the process me-
dium. Avoid pressure surges.
4. Make sure that the pressure rises simulta-
neously upstream and downstream of the
regulator to avoid damaging it.
EB 2559 EN

Advertisement

Table of Contents
loading

Table of Contents