Complete this checklist as the unit is installed to verify that all recommended
procedures are accomplished before the unit is started. This checklist does
not replace the detailed instructions given in the "Installation" section of this
manual! Read the entire section carefully to become familiar with installation
procedures before installing the unit.
Receiving
[ ] Verify that unit nameplate data corresponds with ordering information.
[ ] Inspect unit for shipping damages and material shortages; report any
damages or shortages found to ChillerSource, 800-755-5115.
Unit Location and Mounting
[ ] Inspect unit installation location for adequate ventilation.
[ ] Provide drainage facilities for evaporator water.
[ ] Remove and discard any shipping materials (e.g., cartons, crates, etc.)
[ ] Inspect to determine that service access clearances are adequate.
[ ] Install optional isolation neoprene pad between base and mounting sur-
face.
[ ] Level the unit.
Evaporator Piping
[ ] Flush and clean all chilled water piping.
CAUTION
Pump Damage!
If using an acidic commercial flushing solution, construct a temporary
bypass around the pump and unit. Failure to do so may lead to
equipment damage.