Start-Up And Checkout - Burnham FREEDOM FCM120 Installation, Operating And Service Instructions

Condensing high efficiency direct vent gas - fired hot water boiler
Table of Contents

Advertisement

SAFE LIGHTING AND OTHER PERFORMANCE CRITERIA WERE MET WITH THE GAS
TRAIN ASSEMBLY PROVIDED ON THE BOILER WHEN THE BOILER UNDERWENT
THE TEST SPECIFIED IN Z21.13.
Use the following procedure for initial start-up of the boiler:
1) If not already done, fl ush the system to remove sediment, fl ux, and traces of boiler additives. This should be
done with the boiler isolated from the system.
2) Fill the boiler and hydronic system with water meeting the following requirements below (also see the note on the next
page):
pH between 6.5 and 8.5
Total Solids less than 2500 PPM
Hardness less than 120 PPM (7 Grains/Gallon)
Pressurize the system to at least 12 psi at the boiler
3) Check all new piping for leaks and purge piping sections that are fi lled with air. See the National Fuel Gas Code for
additional information on testing and purging gas lines.
• NEVER USE A FLAME TO CHECK FOR GAS LEAKS.
• MAKE SURE THAT THE AREA AROUND THE BOILER IS CLEAR AND FREE FROM
COMBUSTIBLE MATERIALS, GASOLINE AND OTHER FLAMMABLE VAPORS AND
LIQUIDS
4) Vent system must be complete and free of obstructions before attempting to fi re boiler. Make sure that the silicone cure
time called for in the vent assembly instructions has passed before fi ring boiler.
5) Inspect all line voltage wiring for loose or uninsulated connections.
6) Remove the dust cap from the condensate trap (Fig 7.21). Add water to the trap until water runs out the condensate
drain. Reinstall the dust cap.
XI Start-up and Checkout
NOTE
WARNING
NEVER ATTEMPT TO FILL A HOT EMPTY BOILER
WARNING
47