Installation Of Outdoor Unit; Connection Of Refrigerant Pipings - Mitsubishi Heavy Industries SRK10CFV-4 Technical Manual & Parts List

Room air-conditioning wall mounted type room air-conditioner (split system, air cooled cooling only type)
Table of Contents

Advertisement

5.3 Installation of outdoor unit

(1) Make sure that the unit is stable in installation. Fix the unit to
stable base.
(2) Perfrom wiring, making wire terminal numbers conform to ter-
minal numbers of indoor unit terminal block.
1
Brown
For power supply, indoor outdoor
For power supply, indoor outdoor
2
Blue

5.4 Connection of refrigerant pipings

(1) Preparation
Keep the openings of the pipes covered with tapes etc. to prevent dust, sand, etc. from entering them.
(a) Indoor unit side
(Do not
turn)
¡ Remove the flared nuts.
(on both liquid and gas sides)
(2) Connection of refrigerant piping
(a) Indoor unit side
• Connect firmly gas and liquid side
pipings by Torque wrench.
Spanner
for fixing
the piping)
Torque
wrench
• Specified torquing value:
Liquid side (ø6.35)
Gas side (ø9.52)
Gas side (ø12.7)
• Always use a Torque wrench and back up spanner to tighten the flare nut.
(3) Air purge
(a)
Tighten all flare nuts in the pipings both indoor and outside wall so as not to cause leak.
(b) Connect service valve, charge hose, manifold valve and vacuum pump as is illustrated below.
(c)
Open manifold valve handle Lo to its full width, and perform vacuum or evacuation.
Continue the vacuum or evacuation operation for 15 minutes or more and check to see that the vacuum gauge reads – 0.1 MPa
(– 76 cmHg).
(d) After completing vacuum operation, fully open service valve (Both gas and liquid sides) with hexagon headed wrench.
(e)
Detach the charge hoses.
(f)
Check for possible leakage of gas in the connection parts of both indoor and outdoor.
Stop valve
(Two-way valve)
All manuals and user guides at all-guides.com
(b) Outdoor unit side
Remove
¡ Remove the flared nuts.
(on both liquid and gas sides)
(b) Outdoor unit side
: 14~18N·m (1.4~1.8kgf·m)
: 34~42N·m (3.4~4.2kgf·m)
: 49~61N·m (4.9~6.1kgf·m)
-76 cm Hg
Handle Lo
(pressure)
Stop value
(Three-way
value)
Service port
Charge hose
24
-
Press
Remove
¡ Install the removed flared nuts to the pipes to be
connected, then flare the pipes.
• Connect firmly gas and liquid side
pipings by Torque wrench.
• Specified torquing value:
Liquid side (ø6.35)
: 14~18N·m (1.4~1.8kgf·m)
Gas side (ø9.52)
: 34~42N·m (3.4~4.2kgf·m)
Gas side (ø12.7)
: 49~61N·m (4.9~6.1kgf·m)
• Use one more spanner to fix the valve.
Compound
Pressure
Manifold
(Gauge)
gauge
Valve
Handle Hi
(pressure)
Charge hose
Vacuum pump
-
Terminal block
1 2
Interconnecting wire
Dimension A
Liquid side
(ø6.35): 9.0 dia
Gas side
(ø9.52): 13.0 dia
(ø12.7): 16.2 dia

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Srk13cfv-4Src10cfv-4Src13cfv-4

Table of Contents