10.2 Maintenance schedule

Maintenance
Wear part replacement
Cleaning
Functional test
Visual inspection
Leakage test
* based on 7 bar(g) (101.5 psi(g)) and pH-neutral condensate
INFORMATION
i

10.3 Maintenance work

For maintenance work to be carried out, the following prerequisites must be fulfilled and the preparatory tasks must 
have been completed.
Tools
Screwdriver – flat head
size 2.5 mm (0.09")
Spanner or adjustable end wrench
1.
Decommissioning and disassembly of the BEKOMAT
48 | 76
Interval
After 8760 operating hours or 1 million switching cycles*; at least annually
Annually
Monthly
Weekly
After assembly and maintenance works on the product
Carrying out cleaning work
Carry out cleaning work during wear part replacement since all parts are disassembled at
this point.
Prerequisites
Sealants
Suitable lubricant for greasing the
O-rings
Mild cleaning agent
Cotton or disposable cloth
Preparatory tasks
Original installation and operation manual
Material
have been completed.
®
Protective equipment
Always to be worn:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Bm16ico

Table of Contents